That t he Committee (a) Scrutinise the progress that had been made in managing the risks identified within the Strategic, Operational, Project and Partnership Risk Registers where applicable. (b) Note the new risks that had been identified between October to December 2013. (c) Identify, as appropriate, risk profiles to be scrutinised in more detail for the next meeting.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide an update to Members of the progress made by the Council in enhancing and embedding risk management for the period October to December 2013, including progress made in managing the identified corporate risks.
Recommendations
The Committee is asked to:-
(a) Scrutinise the progress that has been made in managing the risks identified within the Strategic, Operational, Project and Partnership Risk Registers where applicable.
(b) Note the new risks that have been identified between October to December 2013.
(c) Identify, as appropriate, risk profiles to be scrutinised in more detail as part of your responsibility at the next meeting.
Reasons
The risk management process previously adopted by the council has been reviewed to incorporate changes in the way the council works and to provide continuity and streamlined reporting of risks to the necessary stages so that it becomes further embedded at each level of the authority. This will further develop the identification of key risks that potentially threaten the delivery of the corporate priorities. The new Risk Management Strategy will provide a formal and proportionate framework to manage these identified risks and thus reduce the council’s exposure.
To assist the council in its corporate ambitions by helping deliver effective corporate governance, this proactive approach also helps demonstrate good risk management in terms of evidencing that effective risk management is further embedded within corporate business processes.
Background
1.1The council monitors and manages all its risks through the various risk profiles contained within GRACE (Governance Risk and Control Environment) – the council’s software for recording and managing risk.
The council currently reviews its High Red 9 risks at least monthly and its Medium Amber risks at least quarterly.
The last review of these risks was reported to the Council’s Audit & Risk Committee in November 2013.
Risk owners are challenged by the Risk Champions in respect of controls, further actions, ratings and emerging risks and challenge reasons for inclusion or non-inclusion and amendment of these. Projects are managed to a high level in relation to risk and are reviewed in accordance with the Risk Management Strategy – monthly.
2. Issues
2.1Strategic, Operational, Project and Partnership Risk Registers (Appendices)
The Council regularly reviews and refreshes its risk registers in accordance with the Risk Management Strategy. This is co-ordinated by the Strategic Risk Champion who works closely with the Directors, Operational Risk Champions and the Risk Owners.
The risk map below shows the descriptions of the ratings, for ease of use.
L 7 8 9 I High 3 Amber Amber High Red K E 4 5 6 L Medium 2 Green Amber Amber I H 1 2 3 O Low 1 Green Green Amber O D Low 1 Medium 2 High 3
IMPACT
During this quarter there have been no additional risks added of a final rating of Medium 7, 8 or High 9.
Officers have mitigated certain strategic risks in their profiles for this quarter, and have closed a risk. Details of this and the reason why can be seen below.
High red risk regarding reputation damage has been closed by the Chief Executive, with the following explanation –
• The risk has been reviewed and in light of the control measures which have been introduced, and which now form part of organisational operational practice, it is considered that this risk can now be closed. This matter is a risk to the council, but remains part of routine operation which is constantly reviewed. All formal reports of the council, including all key decisions are also subject to a risk assessment.
High red risk regarding the failure of the overall budget realisation failing has been reduced to a medium amber 6 by the Executive Director – Resource and Support Services, with the following explanation –
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit and Standards Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
Draft statement of accounts 2025/26( i ) That the General Fund outturn and key issues in respect of the Council’s financial position at 31 March 2026, b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.