(a) That the contents of the report be noted; (b) That Cabinet agrees with the principle that the Council, as a first resort, will seek to fund its future known capital programme needs through the annual asset management planning process by the identification of land or property in its ownership that is capable of, and appropriate for, disposal; (c) That officers report back to the next Cabinet meeting with a list of potential development sites to be used as the basis for a formal response by the Council as a land owner to the local planning authority’s “call for sites” (as part of the Local Plan process) and used as a basis for programming future land/property disposals through annual Asset Management planning, beginning with the Asset Management Strategy 2015/16; (d) That the principle of engaging a development partner to bring forward the larger sites be agreed.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
(b) That Cabinet agrees with the principle that the Council, as a first resort, will seek to fund its future known capital programme needs through the annual asset management planning process by the identification of land or property in its ownership that is capable of, and appropriate for, disposal;
(c) That officers report back to the next Cabinet meeting with a list of potential development sites to be used as the basis for a formal response by the Council as a land owner to the local planning authority’s “call for sites” (as part of the Local Plan process) and used as a basis for programming future land/property disposals through annual Asset Management planning, beginning with the Asset Management Strategy 2015/16;
(d) That the principle of engaging a development partner to bring forward the larger sites be agreed.
Reasons The Council has significant investment needs over the next four years (and beyond) whilst the resources available to fund this investment fall considerably short of what is required. It is necessary, therefore, to consider options for meeting this shortfall and propose the most effective means to achieve this to a future Cabinet meeting for approval. Because of the size of the shortfall and the early need to fund investment, this needs to be done as soon as practicable.
Background
1.1The Cabinet considered a report at its meeting on 5 February 2014 ‘Newcastle Capital Investment Programme’. This report set out a comprehensive list of the known or likely capital expenditure requirements which the Council will be required to fund over the next 4 years. It provided comprehensive data down to individual scheme level and also indicated the timescale within which such expenditure would be required to be committed (acknowledging that in some instances the Council is not obligated to proceed with the schemes).
1.2This report highlighted that currently the council’s capital resources are very limited. It recorded that at its meeting on 15 January 2014 the Cabinet had approved the marketing for sale of a number of sites which could realise capital receipts of up to £8m in the
foreseeable future. It also noted other sources of potential capital income but as these sources are at this stage undefined, since they relate to Section 106 or partner contributions, these cannot be quantified or considered to be confirmed.
1.3In relation to the current capital programme the February report set out a set of strategies and actions required to deal with the possible shortfall of resources to meet the programme of capital works set out in the report. This work is in hand and an Assets Review Group chaired by the Chief Executive has been established to bring forward this programme.
1.4However, whilst work to review capital demands will assist the Council to prioritise future capital expenditure, it will not address the widening gap between the potential capital expenditure demands and the sources of funding which the Council has to meet these commitments.
2. The Council’s Capital Programme and other capital requirements
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.