Resolved
- That Paul Chatwin , Project Manager, Superfast Staffordshire to be invited back to the next meeting to provide an update on proceedings.
Economic Development and Enterprise Scrutiny Committee decided this item on Wednesday 18 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
- That Paul Chatwin , Project Manager, Superfast Staffordshire to be invited back to the next meeting to provide an update on proceedings.
Update on the Superfast Staffordshire Project Paul Chatwin, Project Manager
The project is making good progress to date, and a total of 178 cabinets have been upgraded giving access to superfast broadband services to 31,239 premises across Staffordshire.
The situation in Newcastle under Lyme see the 66 original structures grow to 71, due to a reallocation of funds within the project. 27 of these structures within the district have been planned (blue), with 6 completed and available for service (green) serving 519 premises. I have attached a list of all the cabs and associated addresses, so you can see the geographic spread. It is anticipated that the balance of the planned cabs will be delivered by the end of June 2015. The unplanned cabs will be planned over the coming quarters, and delivered by June 2016.
More information can be gained, along with an interactive map and postcode checker at the www.superfaststaffordshire.co.uk website. In addition as cabs become available for service we Tweet @superfaststaffs .
I have attached a list of the cabs within the district for your reference. Hope this helps. Regards
Paul
Paul Chatwin Superfast Staffordshire Project Manager
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Superfast Staffordshire ProjectReport | 18 KB | DownloadRead as text |
Follow Economic Development and Enterprise Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2018 | Minutes of previous meetingThat the minutes of the meeting held on 18 September, 2017 be agreed as a correct record. | Agreed | Open |
| 21 Mar 2018 | Future use of land associated with the ryecroft developmentThat the information be received and the comments noted. | Noted | Open |
| 21 Mar 2018 | District dealThat the information be received and the comments noted. | Noted | Open |
| 21 Mar 2018 | Economic performance of the boroughThat the information be received and the comments noted. | Noted | Open |
| 18 Sep 2017 | Minutes of previous meetingThat the minutes of the meeting held on 21 June 2017 be agreed as a correct record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.