( i ) That good progress of the project and note potential project issues be noted. (ii) That the additional costs of the works to the depot and equipment, and the additional expenditure on vehicles, being added to the current capital programme in accordance with the Council’s Financial Regulations be agreed. (iii) That the financial implications in respect of the capital expenditure as outlined in paragraph 7.0 be noted.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To highlight the processes associated with the development of the new Recycling and Waste Service from July 2016 onwards.
To understand the requirement and availability of an appropriate capital budget.
To highlight the risks associated with the provision of the proposed service.
Recommendations
1. That Cabinet note the good progress of the project and note potential project issues.
2. That Cabinet agrees to add the additional costs of the works to the depot and equipment, and the additional expenditure on vehicles, to the current capital programme in accordance with the Council’s Financial Regulations.
3. That Cabinet note the financial implications in respect of the capital expenditure as outlined in paragraph 7.0.
Reasons
To ensure continuity of service at the end of the current contract periods.
To develop a service that provides residents an affordable, environmentally sound, excellent, and legally compliant service.
To ensure approval is in place to undertake procurement in a timely manner.
To provide the council with timely information regarding potential investment pressures and savings that will result from the adoption of a new service.
To ensure that there is adequate time for review, consultation, procurement and implementation of the new service.
To provide a stable platform to enable the Council to maintain and develop the recycling and waste service and to further increase its recycling rates. 1.0 Background
In July 2014, Cabinet agreed the format of the new Recycling and Waste Service post July 2016. The agreed service was Weekly Kerbside Sort Recycling, Weekly Food, Fortnightly Residual and Fortnightly Garden waste collections.
Three 55L box system for dry recycling collected weekly. Paper/Small Electrical appliances/Batteries/Textiles Card/Glass Plastic Bottles/Cans & Tins Food Waste collected weekly – in caddy Garden Waste collected fortnightly – 240L bin Residual Waste collected fortnightly – 180L bin Dry Recycling and Food Waste – Single pass with driver plus one or two porters with a kerbside sort vehicle, Residual/Garden Waste collected fortnightly – with standard collection vehicle
The Cabinet also agreed to the continued use of a Cabinet Panel on political proportionality, and chaired by the Portfolio Holder for Environment and Recycling. The Cabinet also agreed to the recommendation that the Cabinet Panel be given delegated powers to develop and agree the detail of the service and monitor progress of key tasks to be undertaken in the run up to the new service commencement. This includes:-
Specification and procurement of vehicles, Procurement treatment contracts, Depot infrastructure reorganisation. Specification and procurement containers, Material resale arrangements, Collection schedules. Staff working patterns Expansion of the range of materials collected.
2.0Issues
The development of the new service is currently progressing in line with the project plan as agreed by the Cabinet Panel. Officers are currently working on a number of sub projects to ensure that the service is delivered on time. The following will provide an overview of sub projects and highlight issues for cabinet to address. From the four sub projects below, there are three areas that require funding approval from the Cabinet to ensure that the project is delivered on time. Full Council was made aware of this likely cost in the budget report presented at the 25th February 2015 meeting. This report is now seeking approval to start procurement and placement of orders for the following items due to the long lead in time these items attract
2.1Staffing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.