Asset Policy Committee noted this item on Wednesday 16 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
To provide members with an update in respect of the “Newcastle Capital Investment Programme” (NCIP), identifying the investment required over the next four years.
2.1That the Assets Policy Committee endorses the process that has been followed in the compilation of the capital investment programme recognising the need for substantial resources to be identified to fund the programme.
3. Reasons
3.1To set out the capital expenditure required for which funding will need to be made available.
4.1In February 2014 Cabinet approved a report entitled the “Newcastle Capital Investment Programme (NCIP)” which was subsequently endorsed by full Council as part of the approval of the Capital Strategy in February 2015.
4.2The NCIP report set out the investment needed over the period spanning 2015/16 to 2018/19 that would need to be financed by the Council from its own resources:
to replace or maintain operational assets so that services can continue to be provided in accordance with corporate priorities; to ensure the safety and comfort of staff and customers; to comply with statutory provisions eg health and safety, disabled facilities grants; to maintain the stock of investment assets such as shops and industrial units in order to comply with landlord responsibilities and to safeguard future investment income from these assets; to fulfil its environmental and heritage responsibilities.
4.3Over the 4 year period the total investment required, grouped into six themed categories, was estimated at £18.859m. 4.4 The programme did not include the provision of new facilities or other development expenditure, for example in respect of economic development activities or a modern leisure facility in Kidsgrove or investment in the Museum with a view to it being in a condition where it would be feasible to transfer it to a Trust in 5 years’ time.
4.5As discussed at last week’s committee meeting, the intention of this item is not to go through any of the detailed expenditure but for members to note and acknowledge the processes in place that identify the significant future capital investment need.
5. Updating and Reassessment of Capital Expenditure
5.1Since the February 2014 Cabinet report was agreed, the investment needs have been reassessed, firstly when the capital programme for 2015/16 was compiled and secondly following the establishment of the Assets Review Group (ARG). The ARG reviewed the programme and has commenced a process of prioritisation. In addition, a further year (2019/20) has been added to ensure a rolling 4 year programme. Furthermore, new projects have been approved during the last few months and added to the programme (eg the new waste and recycling service and the Civic Hub).
5.2The table below shows the estimated investment required over the next four years:
Investment Type 2016/17 2017/18 2018/19 2019/20 Totals £’000s £’000s £’000s £’000s £’000s Improving Housing in 515 540 540 540 2,135 the Borough Investing in 582 1,034 893 325 2,834 community facilities Community centres 62 505 118 25 709 Safeguarding the 65 136 159 139 499 Borough’s heritage Investing for the future 2,997 689 1,018 1,776 6,480 Vehicles and Plant 2,186 880 204 573 3,843 TOTAL 6,406 3,784 2,931 3,378 16,500
5.3A reconciliation of the changes between the requirement in the February 2014 report, referred to in paragraph 4.3, and the investment now required, as identified in the table above, is shown below:
DETAIL £’000 CAPITAL INVESTMENT PROGRAMME 2015/16 TO 2018/19 18,859 APPENDED TO 2015 TO 2019 CAPITAL STRATEGY CHANGES:
Included in 2015/16 Capital Programme (1,235)
Projects Deleted: Works re Properties to be disposed of as part of Civic Hub (1,301) development Works re Properties Sold (975)
Other Deletions (1,212)
New Projects 1,471
Projects put back to 2019/20 or later (3,535)
Changes to Estimated Costs of Projects (850)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planned Capital ExpenditureReport | 83 KB | DownloadRead as text |
Follow Asset Policy Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jan 2016 | Minutes of the Previous MeetingThat the amendments to the minutes be agreed. | Agreed | Open |
| 6 Jan 2016 | Minutes of the Previous Meeting.That the minutes of the previous meeting be agreed as a correct record. | Agreed | Open |
| 6 Jan 2016 | Confirmation of the Terms of Reference.That the revised draft terms of reference for the Assets Policy Committee be agreed. | Agreed | Open |
| 6 Jan 2016 | Draft Asset Policy.That the information be received. | Decided | Open |
| 16 Dec 2015 | Minutes of the Previous MeetingThat the minutes of the meeting held on 9 December, 2015 be agreed as a correct record subject to the following amend... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.