( i ) That the progress that has been made in managing the risks identified within the Strategic, Operational, Project and Partnership Risk Registers, where applicable, be noted. (ii) That the number of overdue risks be noted. (iii) That the two risk level increases be noted. (iv) That the point stating that no new risks had been identified, be noted.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To inform Members of the progress made by the Council in enhancing and embedding risk management for the period July to September 2016 (Q2), including progress made in managing identified corporate risks.
Recommendations
The Committee is asked to:-
(a) Scrutinise the progress that has been made in managing the risks identified within the Strategic, Operational, Project and Partnership Risk Registers, where applicable.
(b) Note the point 2.1.1 showing the number of overdue risks.
(c) Note the point 2.2.1 advising of 2 (two) risk level increases.
(d) Note the point 2.2.2 regarding no new risks identified between July to September 2016.
(e) Identify, as appropriate, individual risk profiles to be scrutinised in more detail at the next meeting of the Committee.
Reasons
The risk management process previously adopted by the Council has been reviewed to incorporate changes in the way the Council works and to provide continuity and streamlined reporting of risks to allow the process to become further embedded at each level of the authority. This will also aid the identification of key risks that potentially threaten the delivery of the Council’s corporate priorities. The Risk Management Strategy provides a formal and proportionate framework to manage these identified risks and thus reduce the Council’s exposure.
1.1The Council monitors and manages all its risks through the various risk profiles contained within GRACE (Governance Risk and Control Environment) – the Council’s software used to record and manage risks.
1.2The Council currently reviews its high (red 9) risks at least monthly and its medium (amber) risks at least quarterly.
1.3The last review of these risks (Q1 2016) was reported to the Council’s Audit & Risk Committee in September 2016.
1.4Risk owners are challenged by the Council’s Risk Champions in respect of the controls, further actions, ratings and emerging risks related to their risks, and are also challenged on the reasons for inclusion or non-inclusion and amendment of these.
1.5Projects are managed to a high level in relation to risk and are reviewed in accordance with the Risk Management Strategy (i.e. at least monthly).
2. Issues
2.1Further to an Audit Assurance recommendation, your officer has been asked to report on overdue risk reviews that are 6 months out of date.
2.1.1 At the time of running the report, there were no overdue reviews.
2.2Following a previous meeting a brief point is now produced to show any risks where the risk level has increased.
2.2.1 Your officer can report that there has been 2 (two) risk level increases during the period July to September 2016. These can be seen in Appendix A.
2.2.2 There have been no new risks added to any profiles during July to September 2016.
2.2.3 Should there be any increase during October to December 2016 these will be reported to the next Committee meeting.
3. Strategic, Operational, Project and Partnership Risk Registers (Appendices)
3.1The Council regularly reviews and refreshes its risk registers in accordance with the Risk Management Strategy.
3.2These reviews are co-ordinated by the Strategic Risk Champion who works closely with Directors, Operational Risk Champions and Risk Owners.
Follow Audit and Standards Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
Draft statement of accounts 2025/26( i ) That the General Fund outturn and key issues in respect of the Council’s financial position at 31 March 2026, b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.