Resolved
Agreed That the report be received.
Finance, Resources and Partnerships Scrutiny Committee agreed this item on Monday 27 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed That the report be received.
To inform the Committee of the current proposals being considered to balance the 2018/19 revenue budget.
a) That the Committee note the proposals as set out in the appendix to the report.
b) That the Committee identify any areas where further information is required for consideration at its meeting in January.
c) That the Committee suggest any further areas of savings that should be considered.
Reasons
To enable the Committee to review the proposals and to determine whether further information is required on any of the proposals.
1.1The Council’s updated Medium Term Financial Strategy and Efficiency Plan for 2018/19 to 2022/23 was approved by Cabinet on 18 October 2017 and considered at your last meeting on 5 October. It indicated that there will be a budget “gap” of £1.535m in respect of 2018/19 and that this will need to be closed in order to produce a balanced budget.
1.2Over the 10 years from 2008/09 to 2017/18 £22.010m of “gaps” will have been met via a combination of savings, efficiencies and additional income, as shown in the table below:
Year £m £m 2008/09 1.250 2009/10 2.572 2010/11 2.389 2011/12 2.655 2012/13 2.621 2013/14 1.783 2014/15 2.100 2015/16 2.078 2016/17 1.834 2017/18 2.728 2. Proposed Savings and Funding Strategies to eliminate the Budget Gap for 2018/19
2.1The Budget Review Group and your officers have been identifying and considering ways of eliminating this gap. As a result of this work, a number of savings and funding strategies have been identified and agreed with managers as being feasible and sustainable. The proposals are outlined in the table below and set out in detail in the attached Appendix to enable the Committee to review them and determine whether any further information is required on any of the proposals for consideration at its meeting in January. Further work is still ongoing to identify further savings.
Category Amount Comments £’000 Procurement 50 Rationalisation of Multi-Function devices and negotiation of contract pricing Staffing Efficiencies 270 No redundancies are anticipated to arise from these proposals Good Housekeeping Efficiencies, 268 Various savings arising from more efficient General Other Savings, Changes use of budgets in Base Budgets Alternative Sources of Finance/ 688 New Homes Bonus funding, savings from Other Savings negotiated contribution rates and advanced payments of superannuation contributions, effect of forecast Council Tax Base increase, savings from Parish Council concurrent functions contributions, capitalisation of equipment purchases. An assumed £5 (per band D equivalent) increase in Council Tax. Total 1,276
2.2This still leaves a shortfall of £0.259m to be identified (£1.535m current forecast MTFS ‘gap’, less £1.276m savings and funding strategies).
3. Timetable
3.1Set out in the table below are the key dates of the events still to take place before the budget for 2018/19 is finally approved.
When Who What 27 November FRAPSC First review of draft savings plans Mid-Late December All Local Government Financial Settlement 17 January Cabinet Consideration of draft budget proposals 24 January FRAPSC Scrutiny of the draft budget proposals 7 February Cabinet Final budget proposals to be recommended for approval by Full Council 21 February Full Council To approve the budget
FRAPSC – Finance, Resources and Partnerships Scrutiny Committee
4. List of Appendices
Appendix 1: Savings and Funding Strategies 2018/19 Savings and Funding Strategies BEING CONSIDERED (will require robustness checks and final review) Appendix 1
% of Ref Service Area Description £000's Budget Detail Line(s) Procurement Rationalisation of number of devices following the move to Castle P1 Communications Multi-Functional Devices 50 67.6% House, and entering into a new contract 50
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
REVENUE BUDGET 2018/19: FIRST DRAFT SAVINGS PLANSPlan | 89 KB | DownloadRead as text |
Follow Finance, Resources and Partnerships Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jan 2018 | Minutes of previous meetingThat the minutes of the meeting held on 27 November 2017 be agreed as a correct record. | Agreed | Open |
| 24 Jan 2018 | Treasury Management Strategy 2018-19Agreed: The Committee approved the strategy for submission to Full Council on 21 February 2018. | Agreed | Open |
| 24 Jan 2018 | Revenue and Capital Budgets 2018-2019Agreed: That the budget for replacement of waste bins be examined further by Cabinet. | Agreed | Open |
| 24 Jan 2018 | Date of next meetingIt was agreed that, due to a lack of business to be transacted, the next meeting of the Finance, Resources and Partne... | Agreed | Open |
| 27 Nov 2017 | Minutes of previous meetingThat the minutes of the meeting held on 5 October 2017 be agreed as a correct record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.