(i) That the Chief Executive be authorised (and inform the Cabinet Member for Environment and Recycling) to extend the existing contract for the technical consultancy support for the air quality local plan and the contract for the provision of the joint air quality project manager to meet Ministerial Direction relating to Air Quality. (ii) That delegated authority be granted to the Chief Executive (in consultation with the Cabinet Member for Environment and Recycling) for any further extension to the existing contracts for the technical consultancy support or project manager in order to meet the requirements of the Ministerial Direction in relation to Air Quality.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To approve the extension to an award of a contract for the Air Quality Local Plan Technical Consultant work and to approve the award of contract for the air quality project manager.
Recommendations
That the Chief Executive be authorised (and inform the Cabinet Member for Environment and Recycling) to extend the existing contract for the technical consultancy support for the air quality local plan and the contract for the provision of the joint air quality project manager to meet Ministerial Direction relating to Air Quality.
That delegated authority is granted to the Chief Executive (in consultation with the Cabinet Member for Environment and Recycling) for any further extension to the existing contracts for the technical consultancy support or project manager in order to meet the requirements of the Ministerial Direction in relation to Air Quality.
Reasons
To carry out a transport, air quality and economic assessment of a range of measures in order to identify a preferred option for achieving compliance with the legal limits in the shortest possible time as mandated by JAQU (Joint Air Quality Unit - DEFRA / Department of Transport) as a key part of the production and delivery of the Outline Business Case and Full Business Case to JAQU.
Background
1.1The Borough of Newcastle-under-Lyme and City of Stoke-on-Trent, like many areas across the UK, continues to experience areas of poor air quality. The relevant Councils were highlighted by DEFRA as two of a number of Local Authorities where the UK’s national air quality assessment has identified road links that are currently exceeding the annual mean nitrogen dioxide (NO2) limit value, with exceedances predicted to continue in 2019 and beyond.
1.2In October 2018, Ministers Coffey and Norman for the Department for Environment, Food and Rural Affairs (DEFRA) and Department for Transport (DfT) respectively, served the ministerial direction on the Council; this was served under the provisions of The Environment Act 1995 (Feasibility study for nitrogen dioxide compliance) (No 2). This work is being co- ordinated by the Joint Air Quality Unit (JAQU).
1.3The Ministerial directions formally mandate several local authorities (including Newcastle- under-Lyme Borough Council) to undertake further work with the main objective being to explore options for reducing levels of nitrogen dioxide in the air.
1.4The direction requires:
Newcastle-under-Lyme Borough Council and Stoke-on-Trent City Council to jointly further investigate EU exceedances of nitrogen dioxide (NO2) on roads within the Borough and identify measures that could bring forward compliance with NO2 limits as soon as possible or review the implementation of a chargeable clean air zone.
1.5Cabinet have received four previous reports in respect of this matter; In February Cabinet noted that the Ministerial Direction has been served and resolved that the leader would actively engage to lobby against any charging CAZ on the A53. In March, Cabinet noted the content of the strategic outline case and approved the shortlist of measures to be further evaluated. A report for the procurement of a contractor to assist with the delivery of this project was approved at April’s Cabinet. In July, Cabinet received a report updating progress. In addition, this matter was also reported to Council on 3rd April where the previous Cabinet decisions were reported and it was noted that Cabinet firmly believes that there is a highways/transport solution to help reduce the pollution levels and that any form of parking levy or chargeable CAZ would be damaging to business and our town centre.
2.0Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.