INTERNAL AUDIT PROGRESS REPORT - QUARTER TWO - JULY TO SEPT, 2019

Deferred Finance 1 paper

Audit and Standards Committee deferred this item on Monday 11 November 2019. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

(i) That the report be received. (ii) That deferral of the audits listed in Table 2 of the report, be agreed.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Audit and Standards Committee

Purpose of the report

To report on the work undertaken by the Internal Audit section during the period 1st July to September 2019. This report identifies the key issues raised. The full individual reports issued to Officers contain the key issues and recommendations.

Recommendations

1. That Members consider the report.

2. That Members agree to defer the audits listed in section 3.2 (Table 2) below

Reasons

The role of Internal Audit is to ensure that the Council has assurance that controls are in place and operating effectively across all Council Services and Departments. Where required, recommendations are made and agreed with management to ensure that key controls are well designed and operating effectively which provides assurance as to the efficiency and effectiveness of the system, service or process under review.

Background

1.1The Internal Audit Plan for 2019/20 allows for 365 days of audit work.

1.2This is the second progress report of the current financial year presented to the Committee and the areas that it will cover are as follows;  Actual against planned performance for the first two quarters, demonstrating progress against the plan  Details of audit reviews completed and final reports issued  Outstanding recommendations for audit work previous undertaken  Consultancy and non-audit work The opportunity has been taken to review the format of this progress report to ensure the most appropriate details are provided to the Committee.

2. Performance Against Plan

2.1The Audit & Standards Committee approved the internal audit plan for 2019/20 at the April 2019 meeting. Progress against the annual audit plan (i.e. planned audits completed), is outlined in table 1 over. As at the end of September 2019, of the 32 areas / services of

Classification: NULBC UNCLASSIFIED 1 Classification: NULBC UNCLASSIFIED scheduled assurance work for 2019/20, 10 (31.2%) had either been completed or were in progress.

Table 1 2019/2020 Planned Audit Activity as at the end of September 2019

Stage No. % Comment Listed at Table 3: July to Audits completed 2 6.2% September 2019 Audits in progress 8 25.0% Listed at Table 4 Remaining Audits due this Year 16 50.0% Audits Deferred 6 18.8% Listed in Table 2 Total 32 100.0%

2.2The planned work in progress at the end of September 2019 is outlined at Table 2 below. It is intended that this will be completed during the third quarter of 2019/2020.

3 Issues

3.1Following the most recent review of the plan it has been identified that the percentage of audits completed or in progress is below the expected 50% at the half year stage. The plan is regularly monitored and where necessary revised to take into account both unforeseen and new developments. During the past 6 months the internal audit team have been involved in special investigations which have meant that a number of planned audits have been delayed. Whilst flexibility was included in the original plan to support internal investigations, this has not been sufficient to cover all the work required.

3.2As audit resources are finite, it is important to target resources at areas considered to be high risk (where risk includes potential impact on the delivery of the council’s objectives) and high priority, ahead of medium/low ranked audits. In this way the audit resource will be most efficiently utilised and will produce the greatest benefit. A review has therefore been undertaken and it is proposed that the audits listed in table 2 below are deferred for the reason given in the table.

Table 2 - Audits to be Deferred

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT PROGRESS REPORT: QUARTER TWO: JULY TO SEPT, 2019Report 281 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
PW
Councillor Paul WaringChair, present
KO
Councillor Kenneth OwenVice-Chair, present
MS
Councillor Ms Sylvia DymondCommittee Member, present
MS
Councillor Ms Sarah PickupCommittee Member, present
MS
Councillor Mike StubbsCommittee Member, absent
MG
Councillor Mrs Gillian BurnettCommittee Member, present
BP
Councillor Barry PanterCommittee Member, present
PB
Phil ButtersCo-Optee, present
TB
Ms Tess Barker-Phillips (Grant Thornton)Public, expected
PJ
Phil Jones (Grant Thornton)Public, expected
AB
Annette BaileyOfficer, in attendance
GD
Geoff DurhamOfficer, in attendance

All 17 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. INTERNAL AUDIT PROGRESS REPORT - QUARTER TWO - JULY TO SEPT, 2019This decision
  2. Internal audit charter 2026/27Decided
  3. Proposed internal audit strategy & plan 2026/27Approved
  4. Internal audit progress update q3 2025-26Noted
  5. Internal audit progress update quarter 2 2025/26Noted
  6. Q1 internal audit progress update 2025/26Noted

More from Newcastle-under-Lyme Audit and Standards Committee

All decisions
MeetingDecisionOutcome
29 Jun 2026 Minutes of previous meetingThat the minutes of the meeting held on 27 April, 2026 be agreed as a correct record. Agreed Open
29 Jun 2026 Proposed accounting policies & sources of estimation uncertainty 2025/26( i ) That the proposed Accounting Policies that will form part of the 2025/26 Statement of Accounts, be approved. (i... Approved Open
29 Jun 2026 Draft statement of accounts 2025/26( i ) That the General Fund outturn and key issues in respect of the Council’s financial position at 31 March 2026, b... Noted Open
29 Jun 2026 Annual governance statement 2025/26That the Annual Governance Statement for 2025/26, be approved. Watch the debate here Approved Open
29 Jun 2026 Treasury management annual report 2025/26That the Treasury Management Annual Report for 2025/26 be received, ahead of it being reported to Full Council on 30 ... Decided Open