NEWCASTLE CREMATORIUM - PROPOSED REFURBISHMENT OF THE CREMATORS

Approved Executive 2 papers

Cabinet approved this item on Wednesday 11 November 2020. Below is the council's own wording, with the papers it was decided on.

Item46

Resolved

That: 1. The planned improvements at Bradwell Crematorium be supported. 2. The preferred option is approved and an exception to Council Contract Procedure Rules be agreed to enable a direct award of contract without a call for competition for the refurbishment of the Council’s two cremators by the manufacturer and incumbent service provider as set out in the report.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Recommendation

1. That Cabinet support the planned improvements at Bradwell Crematorium. 2. That the preferred option is approved and an exception to Council Contract Procedure Rules is agreed to enable a direct award of contract without a call for competition for the refurbishment of the Council’s two cremators by the manufacturer and incumbent service provider as set out in the report.

Reasons To ensure that the cremators continue operating at optimum levels for the duration of their anticipated remaining working lifespan, and in particular for the forthcoming winter period which may result in a second wave of the coronavirus pandemic.

Background

1.1The two cremators at Newcastle Crematorium were last replaced in 2009/10 and were relined in September 2014. It was anticipated that full replacement would be required in 2021 and provision had been made in the capital programme, along with annual payments into the Equipment Replacement Fund to cover this cost.

1.2However, due to diligent regular servicing and repair of the cremators since their installation, a recent condition survey concluded that their remaining useful working life expectancy is approximately a further 10 years, subject to continued regular maintenance.

1.3Part of the maintenance requirements for the cremators is the need to reline and re-hearth the machines. The relining is usually required every 4 – 5 years and the re-hearth operation is usually required every 2 - 3 years, if using the traditional thermal brick lining, which is the current system in use within both cremators. One of the cremators is now in urgent need of a reline and new hearth, with an estimated remaining use of 200 cremations (January 2021) before the hearth degenerates to a point where it can no longer be operated correctly and safely. 2. Issues

2.1Facultatieve Technologies, the specialist company who supplied and maintain the machines have recently reviewed the cremators and have estimated that they have an approximate 10 year period of use before they need to be replaced completely. They have also provided options and prices for relining and replacing the hearth for one of the cremators in the same traditional thermal brick materials as currently installed, as well as for a newer industry standard block system for both cremators which has a longer life expectancy between relining and installing new hearths. With the new block system, relining is estimated to be required every 8-10 years or 8,000 – 10,000 cremations and a new hearth would be required every 4 – 5 years or 4,000 – 5,000 cremations. Based on our current levels of use the 10,000 cremations would cover approximately 12 ½ years, before a reline may be required.

2.2The time required to complete the relining works for either option is three weeks, and both cremators would have to be shut down completely for the duration of the work. Therefore it makes financial and operational sense to reline and hearth both cremators during a shutdown period to avoid a further shutdown at a later, not too distant date. Due to the current pandemic and the potential for increased pressure on the cremators if a second wave results in increased mortality rates, it is considered critical that the work to the cremators is programmed as soon as possible.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Exception: Waiver Template Cremator RelineAppendix 1 333 KB Download
PDF
NEWCASTLE CREMATORIUM: PROPOSED REFURBISHMENT OF THE CREMATORSReport 377 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 18 attended
ST
Councillor Simon TaggChair, present
SS
Councillor Stephen SweeneyVice-Chair, present
TJ
Councillor Trevor JohnsonCommittee Member, present
HM
Councillor Helena MaxfieldCommittee Member, present
PN
Councillor Paul NorthcottCommittee Member, present
JW
Councillor Jill WaringCommittee Member, present
DA
David AdamsOfficer, in attendance
AB
Annette BaileyOfficer, expected
MH
Martin HamiltonOfficer, in attendance
CT
Craig TurnerOfficer, expected
JW
Jan WillisOfficer, in attendance
SM
Sian Morris-TaitOfficer, expected

All 18 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. NEWCASTLE CREMATORIUM - PROPOSED REFURBISHMENT OF THE CREMATORSThis decision
  2. Application for minor development - bradwell crematorium, chatterley close, bradwell. newcastle borough council. 26/00422/deem3Approved
  3. Proposed extension to newcastle crematorium grounds and development of adjacent land off chatterley closeAgreed
  4. Proposed extension to newcastle crematorium grounds and development of adjacent land off chatterley closeApproved

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies