That: (a) It is noted that since 2012 there have been a number of long standing and/or significant building defects that have had an adverse impact on the reputation of Jubilee2. It is further noted that since 2017 significant progress has been made to resolve some long standing building issues at Jubilee2 (b) That Officers of the Borough Council alongside Morgan Sindall complete the intrusive Building survey to identify any other unknown building defects that may cause future failures of the fabric of the building or failure of fixed electrical and mechanical plant or equipment prior to their normal life expectancy. (c) Officers of the Borough Council alongside Morgan Sindall having completed the above survey establish and agree appropriate corrective actions where building defects are identified.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
This report is aimed at providing an overview of the work undertaken by officers to develop and sustain the Council’s Jubilee2 leisure facility, highlighting the formal governance arrangements during the construction process and the significant building issues faced post construction.
1. Since 2012 there have been a number long standing and or significant building defects that have had an adverse impact on the reputation of Jubilee2. It is therefore noted that since 2017 significant progress has been made to resolve some long standing building issues at Jubilee2
2. That Officers of the Borough Council alongside Morgan Sindall complete the intrusive Building survey to identify any other unknown building defects that may cause future failures of the fabric of the building or failure of fixed electrical and mechanical plant or equipment prior to their normal life expectancy.
3. Officers of the Borough Council alongside Morgan Sindall having completed the above survey establish and agree appropriate corrective actions where building defects are identified.
Reasons
The Council made a significant capital investment in providing Jubilee2. Maintaining the facilities in a good condition protects this investment for the benefit of the health and wellbeing of residents of the Borough and is essential to support the commercial operation of Jubilee2 as well as the Council’s cross-cutting objectives for its communities.
Background
1.1Governance Arrangements: The general project management of Jubilee2 was supported by the following tiered Structure between August 2009 and January 2012.
• Tier 1 - Project Board: The project board was chaired by the leader of the Council and met on a quarterly basis. This group comprised of the Councils Executive management Team, Cabinet, Key Officers, who made key project decisions in relation to finances, design, significant variations to the project and the project time frame etc.
• Tier 2 - Project Steering Group: This Group was chaired by the then Executive Director for Regeneration and Planning as the project director and met on a monthly basis. It incorporated Senior Officers of the Council with the responsibility to drive the project forward. This group was supported by the external Project Manager GMG Associates who provided advice and guidance on key elements of the project to ensure that it was delivered on time and within budget, and supported recommendations made by the group to the project board.
• Tier 3 - Working Groups: Smaller working groups to focus on key areas of the project such as procurement, communications and funding applications, and making recommendations to the steering group.
1.2Design & Supporting Professional Services: To support the design and development of Jubiee2 the following expert practices were engaged in accordance with the Council procurement procedures:
• William Saunders Architects: principal designer (Subsequently novated to Morgan Sindall); • Furness Partnership: Structural Engineers (Subsequently Novated to Morgan Sindall); • Silcock Dawson: Mechanical and Electrical Engineers; • Sheerwater Consultancy: appointed as Pool Consultants; • GMG Associates: appointed as Project Manager and Employers Agent; • GMG Associates: appointed as Quantity Surveyor; • Silcock Dawson: appointed as BREEAM Bespoke Consultants; • RFS Consultancy: appointed as CDM Coordinator; • Staffordshire County Council: delivered Section 278 Highways Works; • Stoke-on-Trent City Council: delivered Building Control Services;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.