That: 1) The project plan for activities leading up to the new service on 1st April 2023, be approved, noting that regular progress updates will be provided by the Executive Director for Sustainable Environment to the Portfolio Holder for Community Safety and Well-being. 2) The Executive Director for Sustainable Environment be authorised, in conjunction with the Portfolio Holder for Community Safety and Wellbeing, to agree the appointment of a contractor to deliver the Occupational Therapy expertise to the service following a competitive tendering process led by Stafford Borough Council 3) The use of the Dynamic Purchasing System, being developed in partnership with 4 other Staffordshire Local Authorities, be approved for obtaining estimates from suitable contractors for adaptation works.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To request Cabinet authority to proceed with preparations to deliver the Disabled Facility Grants service from 1st April 2023 when the contract for the current service ends.
Recommendation
That Cabinet:
1) Approve the project plan for activities leading up to the new service on 1st April 2023, noting that regular progress updates will be provided to the Executive Director for Sustainable Environment and Operations the Portfolio Holder for Community Safety and Well-being.
2) Authorise the Executive Director for Sustainable Environment and Operations in conjunction with the Portfolio Holder for Community Safety and Wellbeing to agree the appointment of a contractor to deliver the Occupational Therapy expertise to the service following a competitive tendering process led by Stafford Borough Council
3) Approve the use of the Dynamic Purchasing System, being developed in partnership with 4 other Staffordshire Local Authorities, for obtaining estimates from suitable contractors for adaptation works.
Reasons
A Staffordshire County Council contract to provide the Disabled Facilities Grant service via a commissioned service ends on 31st March 2023. The contract will not be extended nor will the service be recommissioned by Staffordshire County Council. There is thus a need to review our options and prepare to deliver the service from 1st April 2023.
Background
1.1Disabled Facility Grants (DFGs) are for home adaptations to promote safe independent living. They can range from a simple stair lift to a ground floor extension for bedroom & bathroom access and can be often life changing for the recipients. Funding comes from Central Government via the Better Care Fund managed by Staffordshire County Council. However the statutory responsibility for their delivery rests with the council. 1.2 During 2017 Newcastle-under-Lyme joined a Staffordshire County Council led procurement exercise for Staffordshire Independent Living Service (SILIS), a Home Improvement Agency that would deliver DFGs throughout the county.
1.3Expected benefits of this were around having a hub of expertise, economies of scale with contractors and the supply chain and ending a perceived postcode lottery throughout the county on funding and timescales.
1.4Staffordshire County Council also took the opportunity to make changes to their Occupational Therapy service removing DFG referrals from their contracted service to be picked up by the SILIS contract.
1.5The SILIS contract was let by Staffordshire County Council to Millbrook Healthcare Limited and began on 01.04.18 with a contract end date of 31.03.23.
1.6The Governance of the contract has been through the SILIS Steering Group made up of local authorities who are part of the contract and Staffordshire County Council. The SILIS Steering Group commissioned contract management support to help in this role.
1.7In autumn 2021 the SILIS Steering Group commissioned a review of the contract and option appraisal for the service post 31.03.23. This concluded that the contract would not be extended or recommissioned by Staffordshire County Council with the service to return to being delivered by the local authorities.
1.8The Local authorities who are part of SILIS Steering Group have sought to work together as much as possible relating to the key common tasks for returning the DFG service to local delivery.
1.9This report relates to the progress in preparing to deliver the service from 31.03.23 and the key joint activities.
2. Issues
2.1In order to return the service to being delivered by the Council there are a number of considerations and preparations. These have been pulled together into a project plan.
Project Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.