(i) That the progress made on the Ryecroft multi-storey project, including timescales for planning application submission and its subsequent construction, be noted. (ii) That the progress made on the wider Ryecroft site against the delivery of the Ryecroft Blue Print, be noted. (iii) That the Executive Director – Development and Growth, in consultation with the Portfolio Holder, Finance, Town Centres and Growth be authorised to enter a Pre-construction Services Agreement with Morgan Sindall for enabling and infrastructure works on the car park and the wider Ryecroft site, to further work up further details for a linear park on Ryecroft and to instruct Morgan Sindall to submit an outline planning application for the Ryecroft Masterplan. (iv) That a further Cabinet Report be presented prior to any construction contracts being awarded for the multi-storey car park. (v) That the new Multi-Storey Car Park on the Ryecroft site will be named ‘Castle Car Park’.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide an update on progress made on the Multi-storey car park project.
Recommendation
That Cabinet
1. Notes the progress made on the Ryecroft multi-storey project, including timescales for planning application submission and its subsequent construction.
2. Notes the progress made on the wider Ryecroft site against the delivery of the Ryecroft Blue Print.
3. Authorises the Executive Director – Development and Growth, in consultation with the Portfolio Holder, Finance, Town Centres and Growth to enter a Pre-construction Services Agreement with Morgan Sindall for enabling and infrastructure works on the car park and the wider Ryecroft site, to further work up further details for a linear park on Ryecroft and to instruct Morgan Sindall to submit an outline planning application for the Ryecroft Masterplan.
4. Note that a further Cabinet Report will be presented prior to any construction contracts being awarded for the multi-storey car park.
5. Agree that the new Multi-Storey Car Park on the Ryecroft site will be named ‘Castle Car Park’.
Reasons
The Council has secured £11m from DLUHC (Department of Levelling up and Housing Communities) from the Future High Street Fund for the redevelopment of the Ryecroft site including the development of a new multi-storey car park.
The Council appointed Morgan Sindall as Design and Build Contractor and it is appropriate to update Cabinet on progress to date and plan for the next stage of investment in this project.
This project is a key step in the key Town Centre developments that are planned through the Future High Street Fund and Town Deal grant monies. 1. Background
1.1In December 2020 MHCLG (now DLUHC) confirmed to the Council that its Future High Street Fund business case submission had been successful and that £11,048,260.00 was approved for Newcastle town centre. In January 2021 the Council submitted confirmation of its acceptance of the grant and detailed that the funding would be used to secure the demolition of the former Civic Offices, design and build a new multi-storey car park, acquire and demolish York Place and undertake public realm works.
1.2In April 2021 the Council agreed to accept the grant offer and funding agreements were signed. A total of £3,500,000 was allocated to the new multi-storey development.
1.3In December 2021 Morgan Sindall were chosen as Design and Build Contractors following a procurement exercise using the Pagabo framework.
2. Update
2.1The Council have been working closely with Morgan Sindall and their design team to develop proposals for the site.
2.2A RIBA Stage 2 report was issued in September 2022 with a RIBA Stage 3 report following in December 2022. Throughout this period pre-application discussions have been held with NuLBC Planners and SCC Highways and the scheme was presented to Design Midlands review panel in December 2022. The application for planning is to be submitted in January 2023 and, assuming consent is granted, construction would commence in May 2023 and completed by March 2024.
2.3The proposed multi-storey car park will deliver 450 new spaces along with 39 Electric Vehicle charging spaces and 11 disability spaces. Access to and egress from the new car park is via Liverpool Road.
2.4The next steps for the car park project are to submit the planning application in mid January 2023 and, assuming planning consent is granted, commence construction in May 2023 with completion anticipated in March 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.