CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newcastle-under-Lyme Borough Council
Cabinet, Tuesday 18 April 2023 at 2.00pm

UNITS 1-18 BRAMPTON SIDINGS ROOFING WORKS

Decided Executive 1 paper

Cabinet decided this item on Tuesday 18 April 2023. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

That the award of contract for roofing works at Brampton Sidings to Total Roofing Solutions and Building Services Ltd of £255,823 for Brampton Sidings roof works be authorised.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Purpose of the report

To request approval to award a contract in excess of £250,000 for the over-cladding works to the existing profiled asbestos cement roof of Brampton Sidings Industrial Units.

Recommendation

That Cabinet authorise the award of contract for roofing works at Brampton Sidings to Total Roofing Solutions and Building Services Ltd of £255,823 for Brampton Sidings roof works.

Reasons

Funding for Brampton Sidings roof of £250,000 has been identified in the 2022/2023 Capital Budget which was approved by Council as part of the budget setting process in February 2022. The budget allocation was put in place to plan for works due to leakage of the Industrial Units roofs, identified in the Stock Condition Review of 2017-2018 and re-Review of the SCR in December 2020, in order to replace end of life exposed building fabric.

Background

1.1As part of a nationally advertised open tender procurement process, the Borough Council invited suitably qualified companies to provide a schedule of prices for the over-cladding to existing profile sheet roof to Units 1 – 18 of Brampton Sidings Workshops.

1.2The need for over-cladding works follows a recent inspection of roof leaks and identification of urgent works to address the issue. Funding for the works having been identified in the Council’s Capital Works Programme.

1.3The works to Brampton Sidings Roof includes:

a. Cleaning of the existing profile roof of moss; b. Installation of a vapour control membrane; c. Installation of galvanised steel sub-frame supporting system; d. Installation of Glass fibre Insulation system with thermal properties of 0.04w/mk; e. Installation of new metal roofing sheet; f. Replacement of all timber fascia boards with aluminium colour coated boards; g. Replacement of all rainwater goods. 2. Issues

2.1To do nothing was not an option, as this would lead to further deterioration of the roof and severely impact on tenants who have been complaining of the roof leaks.

2.2As part of the procurement process, there were 8 listed interested parties and 5 parties that withdrew an interest. On the closing date for the bids to be received:

 2 compliant submissions were received;  2 bids of alternative specification were received with one of the bidders subsequently withdrawing.

2.3The bids were evaluated on the basis of the most economically advantageous tender (40% Commercial and 60% Quality), the outcome of the evaluation can be found below:

Company Commercial Quality Total MEAT Score Bidder ‘A’ Withdrawn Bidder ‘B’ 26.72 48.90 69.47 Bidder ‘C’ 33.10 60.00 93.10 Bidder ‘D’ 40.00 43.94 83.94

2.4Bidder C (Total Roofing Solutions and Buildings Services Limited) with the highest score of 93.10 is the successful bidder.

3. Proposal

3.1That Cabinet authorise the award of contract for roofing works at Brampton Sidings to Total Roofing Solutions and Building Services Ltd of £255,823 for Brampton Sidings Industrial Units roof works. 3.2 Payments are at the end of each month based on measured completed works, signed off as interim certificates to JCT procedure. The defects liability period is 12 months under Contract. The contract will be signed under Seal, with (Contract) Limitation Act 1980, therefore applicable for any subsequent Patent or Latent defects.

3.3The Contracting process will be via a JCT Minor Works Building Contract 2016 and the Contract Administrator will be Professionally Registered parties already appointed for the tender process etc. by the Employer. The Employer under Contract, being the Council.

4. Reasons for Proposed Solution

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UNITS 1-18 BRAMPTON SIDINGS ROOFING WORKSReport 471 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 17 attended
ST
Councillor Simon TaggChair, present
SS
Councillor Stephen SweeneyVice-Chair, present
GH
Councillor Gill HeesomCommittee Member, present
TJ
Councillor Trevor JohnsonCommittee Member, present
JW
Councillor Jill WaringCommittee Member, apologies
AF
Councillor Andrew FearCommittee Member, present
AB
Annette BaileyOfficer, expected
MH
Martin HamiltonOfficer, in attendance
CT
Craig TurnerOfficer, expected
SM
Sian Morris-TaitOfficer, expected
GD
Geoff DurhamOfficer, in attendance
SM
Simon McEnenyOfficer, in attendance

All 17 on the meeting page

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies