KEELE SUSTAINABLE SOLAR ENERGY

Approved Executive 2 papers

Cabinet approved this item on Tuesday 17 October 2023. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

(i) That the production of a detailed feasibility study and business case for the solar array at Keele be approved. Details to be provided through a further report. (ii) That the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres & Growth, be authorised to submit a planning application for the solar array at Keele; (iii) That a further report on the progress and next steps required be received prior to any installation works being undertaken on site or end user agreements are signed.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Recommendation

That Cabinet:-

1. Approves the production of a detailed feasibility study and business case for the solar array at Keele, details to be provided through a further report,

2. Authorises the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres & Growth, to submit a planning application for the solar array at Keele;

3. Receives a further report on the progress and next steps required prior to any installation works being undertaken on site or end user agreements are signed.

Reasons

The Council adopted a Sustainability Environment Strategy in 2020 which states the Council will reduce our reliance on fossil fuels by investigating green energy investment. Following an initial high-level feasibility study the Council has procured planning consultants to design a suitable solar array scheme and to submit a planning application for the facility and associated connection infrastructure. It is therefore appropriate that Cabinet reviews progress in taking forward a suitable scheme and delegates authority to submit a planning application. There will be further Cabinet reports prior to any contracts and licences being awarded for the construction or supply of the energy produced.

1. Background 1.1 The Climate Change Act 2008 places the government under a legal duty to reduce greenhouse gas emissions by 80% below 1990 levels by 2050 and the Council has been working to reduce our emissions since. In 2019 the Council passed a climate emergency motion with the aim of becoming carbon neutral with respect to the Council’s own estates and activities and those related to our residents and businesses. Following this, the Council adopted a Sustainable Environment Strategy in 2020. This Strategy is the vehicle for helping the Council achieve its aims of caring for and enhancing our natural environment and to adapt and mitigate the effects of climate change. It states the Council will reduce our reliance on fossil fuels by investigating green energy investment.

1.2In line with seeking alternatives to greenhouse gas emissions one of major responses nationally has been to seek alternative energy generation. The Council was successful in securing Carbon Reduction Funding (CRF) from the government for four projects, one of which was to consider the feasibility of the Council building a solar array on land it owns adjacent to Keele Cemetery.

2. Issues

2.1As part of the Government funded CRF programme Wardell Armstrong were appointed to do a high level feasibility study to outline if there was potential for a solar array at Keele. The study considered suitability of the site, connection into the electricity grid, and or potential off-takers (end users) for the facility, including the adjacent Cemetery facility.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
KEELE SUSTAINABLE SOLAR ENERGYReport 623 KB DownloadRead as text
PDF
Solar appendix: Site DesignAppendix 6.7 MB Download

At this meeting

Whole meeting

Who was there

6 of 24 attended
ST
Councillor Simon TaggChair, present
SS
Councillor Stephen SweeneyVice-Chair, present
GH
Councillor Gill HeesomCommittee Member, present
AF
Councillor Andrew FearCommittee Member, present
AB
Annette BaileyOfficer, expected
MH
Martin HamiltonOfficer, in attendance
CT
Craig TurnerOfficer, expected
SM
Sian Morris-TaitOfficer, expected
GD
Geoff DurhamOfficer, expected
SM
Simon McEnenyOfficer, in attendance
SH
Simone HarrisOfficer, expected
SW
Sarah WilkesOfficer, in attendance

All 24 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. KEELE SUSTAINABLE SOLAR ENERGYThis decision
  2. Keele sustainable solar energy business caseDecided

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies