TOWN CENTRE REGENERATION UPDATE

Noted Executive 2 papers

Cabinet noted this item on Tuesday 6 February 2024. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

(i) That the progress made to date by Capital&Centric on the York Place, Midway Car Park and The Ryecroft projects in Newcastle Town Centre be noted; (ii) That, subject to Council approval of the funding as set out in Recommendation 3: a. The Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and the Portfolio Holder for One Council, People and Partnerships, be authorised to progress legal agreements to enable the appointment of Capital&Centric under three Pre-Development Services Agreements (PDSA) for the development of the three schemes through a direct award under the Pagabo Development Management Framework. b. That the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and Portfolio Holder for One Council, People and Partnerships, be authorised to enable re-development works to commence on York Place, through Capital&Centric’s PDSA, at a cost not exceeding £500,000 (the cost of which is included in the overall budget). (iii) Recommends that Council approve expenditure of up to £2,649,000 to develop the three schemes to the end of RIBA Stage 3, and the submission of planning applications.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Recommendation

That Cabinet:

1. Notes the progress made to date by Capital&Centric on the York Place, Midway Car Park and The Ryecroft projects in Newcastle Town Centre;

2. Recommend that Council:

a. Approve expenditure of up to £2,649,000 to develop the three schemes to the end of RIBA Stage 3, and the submission of a planning applications;

b. Authorise the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and Portfolio Holder for One Council, People and Partnerships to progress legal agreements to enable the appointment of Capital&Centric under three Pre-Development Services Agreements (PDSA) for the development of the three schemes through a direct award under the Pagabo Development Management Framework;

c. Authorise the Deputy Chief Executive, in consultation with the Portfolio Holder for Finance, Town Centres and Growth, and Portfolio Holder for One Council, People and Partnerships to enable re-development works to commence on York Place, through Capital&Centric’s PDSA, at a cost not exceeding £500,000 (the cost of which is included in the overall budget above).

Reasons

The Council has been developing plans for several key sites across the Town Centre of Newcastle-under-Lyme as part of the Future High Street Fund and Town Deal Fund.

This report enables progress to be made across these sites.

1 1. Background

1.1As reported to previous Cabinet meetings, the Council has secured Future High Street Fund and Town Deal Fund for the re-development of several key regeneration sites across the Town Centre. In September 2023 the Council appointed Capital&Centric to undertake feasibility studies for the re-development of the former York Place Shopping Centre, of the re-development of the Midway Car Park upon its closure in late 2024, and the development plans for The Ryecroft site.

1.2The Process being followed with Capital&Centric, across the three development sites is an incremental one, with Capital&Centric having completed their initial development proposals (RIBA Stage 2) for each of the sites. If the Council is satisfied with the RIBA Stage 2 works, as summarised in this report, and in the attached Appendix, the Council would then use the Pagabo Framework to appoint Capital&Centric to:

 Develop the scheme design and costs for each of the three sites to RIBA Stage 3, under an individual Pre-Development Services Agreement for each site.  Manage the procurement and delivery of re-development works at York Place including stripping out and retaining the concrete frame to suit the design for the overall scheme, again under an individual Pre-Development Services Agreement.  Upon receipt and approval of the fully costed RIBA Stage 3 designs and costs, Council would then determine whether to enter into a further contract for the construction and marketing works on each site.

1.3This incremental approach has been used successfully by the Council on both the Kidsgrove Sports Centre refurbishment and on the construction of the new Castle Car Park. Crucially, it enables the Council to take a phased approach to the developments, with cost certainty secured before progressing to the next stage.

1.4This report deals only with updating on progress to date across the three sites and securing commitment to progressing to RIBA Stage 3 designs, and initial work on the redevelopment of York Place.

2. Update

York Place – Update on Current Position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital&Centric Proposal Newcastle-under-Lyme business case pdfAppendix A 6.2 MB Download
PDF
TOWN CENTRE REGENERATION UPDATEReport 493 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 25 attended
ST
Councillor Simon TaggChair, present
SS
Councillor Stephen SweeneyVice-Chair, present
GH
Councillor Gill HeesomCommittee Member, present
AF
Councillor Andrew FearCommittee Member, present
CS
Councillor Craig SkeldingCommittee Member, apologies
DH
Councillor David HutchisonCommittee Member, present
AB
Annette BaileyOfficer, expected
MH
Martin HamiltonOfficer, in attendance
CT
Craig TurnerOfficer, expected
SM
Sian Morris-TaitOfficer, expected
GD
Geoff DurhamOfficer, in attendance
SM
Simon McEnenyOfficer, in attendance

All 25 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. TOWN CENTRE REGENERATION UPDATEThis decision
  2. Newcastle town centre public space protection order renewalApproved
  3. Business improvement district, newcastle town centre - re-ballotNoted
  4. Newcastle town centre public space protection order renewalAgreed
  5. Newcastle town centre community safety partnershipNoted
  6. Town centre regeneration updateNoted

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies