Resolved : 1. That there were currently no risks that were more than 6 months overdue for a review up to end of Q2 2024/25, be noted. 2. That there had been 3 risk level increases, be noted. 3. That new risk change to the Corporate Risk Register, be noted. 4. That officers be advised of any individual risk profiles that the Committee would like to scrutinise in more details at its next meeting. 5. That whilst the likelihood of a risk materialising may be mitigated, the likely impacts may not change, be noted. Watch the debate here
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1. Note that there are currently no risks that are more than 6 months overdue for a review up to end of Q2 2024/25.
2. Note that there have been 3 risk level increases.
3. Note new risk change to the Corporate Risk Register.
4. Advise officers of any individual risk profiles that the Committee would like to scrutinise in more details at its next meeting.
5. Note that whilst the likelihood of a risk materialising may be mitigated, the likely impacts may not change.
Reasons
To comply with Audit and Risk Management Strategy requirements to report to committee: risk reviews that are more than 6 months overdue; the Corporate Risk Register; and any risks that have been increased in rating to a medium D or high E, or are new risks.
Background
1 1.1 The Council’s Risk Management Strategy (RMS) sets out how it identifies, records, manages and reports on risk. It uses the GRACE software (Governance Risk and Control Environment) to monitor and manage all of its risks by creating individual risk profiles which rank risk based on likely occurrence and impact, after applying relevant mitigation measures. The system allows for the creation and monitoring of mitigation action plans and the assignment of risk owners.
1.2The system allows risks to be managed in this way at service and directorate level and, where warranted, corporately through the Corporate Leadership Team and this committee. The RMS describes how risks are escalated and reported through that hierarchy depending on the nature of the risk, and in light of any delays in reviewing risk profiles or applying mitigation measures.
1.3The Council currently reviews its high (red) risks at least monthly and its medium (amber) risks at least quarterly. The RMS and good audit practice requires that amber and red risks are reported to this committee where escalation is required, along with any risk profiles that are overdue for review by 6 months or more. This set of measures was last reported to this Committee on 30 September 2024.
1.4GRACE automatically prompts Risk Owners to review their risk profiles at the required intervals, and will escalate overdue reviews. The review process involves the Council’s Risk Champion challenging Risk Owners in respect of the controls, further actions, ratings and emerging risks related to their risk profiles. They are also challenged on the reasons for inclusion or non-inclusion of risks and amendments made to profiles. The Risk Champion has a direct reporting line to the Monitoring Officer and into the Corporate Leadership Team.
1.5Project specific risks are managed to a high level in project specific risk registers, and are reviewed in accordance with the RMS at least monthly. Any specific projects can, where required, also have their risks monitored, maintained and managed in the Project Board meetings, but remain subject to the escalation requirements in the RMS.
2. Issues
2.1There are currently no risk reviews 6 months overdue, up to the end of Q2 2024/25.
2.2During the last quarter (Q2), three risks rose in priority to a Medium D or High E.
2.3The Corporate Risk Register has been reviewed, and there has been one new risk added in relation to Community Cohesion.
2 3. Recommendation
3.1That Members note that there are currently no risks more than 6 months overdue for a review up to end of Q2 2024/25.
3.2That Members note that there have been three risk level increases to either a Medium D or a High E.
3.3That Members note the new risk in the Corporate Risk register. Appendix A shows the status as at 17 October 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit and Standards Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
Draft statement of accounts 2025/26( i ) That the General Fund outturn and key issues in respect of the Council’s financial position at 31 March 2026, b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.