(i) That this report and the successes evidenced, be acknowledged. (ii) That the lessons learned and the need to continuously improve as the One Council programme closes, be acknowledged. (iii) That service level change and delivery of improvement moves into business as usual as teams use the skills they have learned through this process to challenge them selves and others to continue to make positive change, be noted. (iv) That the significant efforts of Council teams involved in the transformation, be celebrated and endorsed. (v) That it be agreed that Agile becomes the espoused project methodology across NULBC, along with knowledge of the tools used to deliver the One Council Programme – Refresher training be offered to Business Managers to ensure the required adoption. (vi) That it be approved that the Benefits Tracker continues to be used to capture opportunities organisation wide to ensure their delivery and inclusion into succession programmes and Efficiency Boards. (vii) That the Programme governance, approach and dashboard model is emulated in the One Council Green, Digital and Commercial follow-on Programmes, be agreed. (viii) That the report be referred to the Finance, Assets and Performance Scrutiny Committee.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1. Acknowledges this report and the successes evidenced.
2. Further acknowledges the lessons learned and the need to continuously improve as the One Council programme closes.
3. Notes that service level change and delivery of improvement moves into business as usual as teams use the skills they have learned through this process to challenge them selves and others to continue to make positive change.
4. Celebrates and endorses the significant efforts of Council teams involved in the transformation.
5. 5.Agrees that Agile becomes the espoused project methodology across NULBC, along with knowledge of the tools used to deliver the One Council Programme – Refresher training be offered to Business Managers to ensure the required adoption.
6. Approves that the Benefits Tracker continues to be used to capture opportunities organisation wide to ensure their delivery and inclusion into succession programmes and Efficiency Boards.
7. Agrees that the Programme governance, approach and dashboard model is emulated in the One Council Green, Digital and Commercial follow-on Programmes.
8. Agrees to refer the report to Finance, Assets and Performance Scrutiny Committee.
1 Reasons
A large scale programme such as the One Council will create lasting change and improvements to services. These changes will not be linear.
Acknowledging where things could have gone better is a valuable learning experience and supports organisational learning and continuous improvement.
Background
1.1The One Council Transformation Programme was Newcastle Borough Council’s biggest ever change programme borne out of both future financial uncertainty and learning from the pandemic when the Borough Council was required to swifty adapt and change. 1.2 The Programme aimed to fundamentally change the Council’s operating model to better meet the needs and demands of our community, to become both more efficient and effective with the resources at our disposal and to provide enhanced customer journeys whilst bringing about annual financial savings of over £1.17m (amounting to 6% of the Council’s net budget) year on year. 1.3 The appendix report summarises the process followed, achievements and lessons learned of the programme and sets the scene for The One Green Council, One Digital Council and One Commercial Council programmes.
2. Issues
2.1In 2020, the Council was facing significant future financial challenges, alongside the operational and strategic challenges of service delivery during the Covid 19 pandemic. 2.2 Taking a forward thinking approach, the Council took the decision to face these challenges head on and embark on a full scale transformation which launched in 2021. 2.3 The transformation delivered a new operating model alongside significant operational efficiencies measured in officer time and delivery cost 2.4 Central to the programme was a focus on culture and behaviours leading to improvements in staff engagement as well as a renewed emphasis on organisational values designed to enhance the delivery of excellent services to residents. 2.5 Teams and services were encouraged and supported to work together in order to create slick and efficient experience for our customers. 2.6 A spend to save model was used with an outlay of £1.2m over the life of the programme, which resulted in overall savings of £1.17m per annum. 2.7 Programme progress was tracked throughout via innovative use of Power BI tools and a ‘benefits tracker’ which supported live tracking and measurement of intended and realised benefits.
3.1It is asked that Cabinet:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.