Newcastle-under-Lyme Borough Council
Cabinet, Tuesday 4 August 2026 at 2.00pm

LYME VALLEY PUMP TRACK

Approved Executive 3 papers

AI summaryCabinet approved public consultation on replacing the Lyme Valley BMX track with a pump track, allocated £135,000 of Section 106 funding, and authorised officers to award a contract within an estimated £150,000 budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConsultation, contract award, and funding allocation all agreed
MoneyNot stated
What happens nextPublic consultation for around 6 weeksOnline and with targeted stakeholders
Who it affectsClayton ward users and visitorsLyme Valley park, wheeled sports community

What was decided

Initial draft design proposals from specialist contractors were approved to go to public consultation. Report P9

The Service Director for Neighbourhood Delivery, in consultation with the Portfolio Holder, was authorised to approve the final design and award the construction contract to the lowest suitable tender, provided total costs stay within the available budget. Report P10

Section 106 funding of £135,000 was allocated to the project, and officers were authorised to keep seeking extra funding to bridge the gap to the £150,000 estimated total cost. Report P11

Why

The existing BMX track is around 20 years old and needs updating to cater for a wider range of wheeled sports such as skateboards, scooters and rollerblades. Report P12, P13

Lyme Valley is a strategic park serving a large catchment, and a pump track would give young people more opportunities for outdoor activity, supporting health and wellbeing. Report P14

A similar pump track was installed at Newchapel Recreation Ground in 2021 and another is under construction at Bradwell Dingle, providing local precedent. Report P12

What happens next

The draft design options will go to public consultation for around 6 weeks, online and with ward members and community groups. Report P13

After consultation, the final design will be approved and the contract awarded to the lowest suitable tender, with an estimated build time of 10 to 12 weeks. Report P13

If funding is secured, the facility is estimated to open in late 2026, managed by the Neighbourhood Delivery Service through a specialist contractor. Report P13

The money

  • £135,000 Identified Section 106 Agreement funding allocated to the project Report P11, P15
  • £150,000 Estimated total capital cost of installing the pump track Report P11, P13, P15

Options considered

  • Chosen: Approve draft proposals for consultation and allocate £135,000 Section 106 funding. Allows the project to proceed to public consultation within the secured budget envelope, with further funding to be sought. Report P9, P10, P11

Implications

  • Financial: There is a risk that scheme costs could exceed the current £135,000 secured budget; officers will continue to seek additional funding and the contractor brief specified a provisional option within £150,000. Report P15, P16
  • Risk: There is a risk of an adverse community response to the consultation; this will be mitigated by siting the pump track on the existing BMX track footprint where such use is already established. Report P16
  • Staffing: Staff resources within the Neighbourhood Delivery Service are limited and have been diverted to this project, which may affect delivery of other projects or workstreams. Report P15

Who and where

  • Residents and visitors to Lyme Valley, Clayton ward Report P5, P12, P14
  • Young people and wheeled sports users (BMX bikes, skateboards, scooters, rollerblades) Report P12, P14
  • Targeted consultation stakeholders including ward members and community groups Report P13

Timeline

  • Around 20 years ago: Existing BMX Track installed in Lyme Valley under the Greening for Growth programme Report P12
  • 2021: Pump track installed at Newchapel Recreation Ground under the Kidsgrove Advance Town Deal Fund Report P12
  • Around 6 weeks from approval: Public consultation on design options to run online and with targeted stakeholders Report P13
  • 10 to 12 weeks: Estimated construction build time after contract award Report P13
  • Late 2026: Estimated opening of the pump track, subject to full funding being secured Report P13

Plain English for the jargon

  • Pump track: A modern facility with a smooth tarmac surface for wheeled sports such as BMX bikes, skateboards, scooters and rollerblades.
  • Section 106 Agreement: A planning obligation under which a developer contributes funds to the council for local infrastructure or facilities.
  • Service Director, Neighbourhood Delivery: The senior council officer responsible for neighbourhood services, including the Landscape and Community Team that will manage the project.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

(i) That the initial draft proposals received from specialist design and build contractors for consultation be approved; (ii) That the Service Director – Neighbourhood Delivery be authorised, in consultation with the Portfolio Holder for Residents Services and Neighbourhoods, to approve the final design having considered the consultation responses, and to award the contract for construction of the facility to the lowest suitable tender subject to the full costs falling within the available budget; (iii) That the identified Section 106 Agreement funding totalling £135,000 be allocated to the project, and that officers be authorised to continue to seek additional funding to bridge the gap to the estimated total cost of £150,000.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Cabinet

Report to Cabinet 04 August 2026

Lyme Valley Pump Track Lead Member: Cllr Andrew Fisher – Portfolio Holder for Residents Services and Neighbourhoods

Lead Officer: Roger Tait – Service Director, Neighbourhood Delivery

Key Decision: Yes

Ward(s): Clayton

Appendices: Initial Design and Costing Proposals for Consultation

Report Assurance: Name Date Lead Officer Roger Tait 24/06/26 Monitoring Officer Olwyn Brown Section 151 Craig Turner 17/07/26 Chief Executive Gordon Mole 17/07/26 Cabinet Member Andrew Fisher Report Summary The report seeks approval to transform an existing BMX Track in Lyme Valley into a modern pump track facility to cater for a range of wheeled sports, and to allocate existing Section 106 Agreement funding to the project. Public consultation will be undertaken online to gauge community views on options for the facility, which have been prepared by specialist design and build contractors.

Recommendations That the Cabinet:

1. Approves the initial draft proposals received from specialist design and build contractors for consultation;

2. Authorises the Service Director – Neighbourhood Delivery, in consultation with the Portfolio Holder for Residents Services and Neighbourhoods, to approve the final design having considered the consultation responses, and to award the contract for construction of the facility to the lowest suitable tender subject to the full costs falling within the available budget;

3. Allocates the identified Section 106 Agreement funding totalling £135,000 to the project, and authorises officers to continue to seek additional funding to bridge the gap to the estimated total cost of £150,000.

1. Background 1.1. The Lyme Valley is one of the Borough Council’s strategic parks, serving a large catchment area and providing a wide range of sporting and recreational facilities to cater for all ages. 1.2. There is an existing BMX Track in Lyme Valley which was installed around 20 years ago as part of the “Greening for Growth” programme which invested in green spaces across the North Staffordshire conurbation as a contributor to economic development. 1.3. Although popular, the BMX Track is in need of updating and remodelling to enable it to cater for other wheeled sports. The more modern version of this type of facility is a pump track, which can be used by BMX bikes, skateboards, scooters and rollerblades. A very successful pump track was installed at Newchapel Recreation Ground in 2021 as part of the Kidsgrove Advance Town Deal Fund, and another pump track is currently under construction at Bradwell Dingle.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LYME VALLEY PUMP TRACKReport 185 KB DownloadRead as text
PDF
Option 1Report 124 KB Download
PDF
Option 2Report 149 KB Download

At this meeting

Whole meeting

Who was there

5 of 21 attended
JG
Councillor Jonathan GullisChair, present
GS
Councillor Graham ShawVice-Chair, present
AF
Councillor Andrew FisherCommittee Member, present
VR
Councillor Vanessa RenshawCommittee Member, present
MR
Councillor Martin RogersonCommittee Member, apologies
BS
Councillor Ben SimpsonCommittee Member, present
GM
Gordon MoleOfficer, in attendance
SM
Simon McEnenyOfficer, in attendance
AB
Andrew BirdOfficer, expected
NB
Nesta BarkerOfficer, expected
GE
Georgina Evans-StadwardOfficer, expected
RT
Roger TaitOfficer, in attendance

All 21 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. LYME VALLEY PUMP TRACKThis decision
  2. Lyme valley car parkingDecided
  3. Lyme valley parkingAgreed
  4. Application for Other Development - Land at Lyme Valley Parkway, London Road, Newcastle. Newcastle Borough Council. 15/00941/DEEM3Decided
  5. Application for Minor Development - Land Opposite Superstore, Lyme Valley Road, Newcastle; Ian Matthews/Robert Berry; 14/00472/FULAgreed
  6. Response to Petition to Protect the Dogs of Lyme Valley Park From Being PoisonedDecided

More from Newcastle-under-Lyme Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of previous meetingsThat the Minutes of the meeting held on the 4 August be agreed as a correct record. Agreed Open
15 Sep 2026 Walleys quarry odour updateThat the contents of the update report be noted. Noted Open
15 Sep 2026 Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi... Noted Open
15 Sep 2026 Recycling & waste re-routing(i) That the recycling and waste collection day changes for approximately 22,000 households in the south of the borou... Approved Open
15 Sep 2026 Improving safety and welfare infrastructure at knutton lane depot(i) That the works and budget necessary to refurbish and upgrade the Knutton Lane depot to improve health & safety we... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies