Newcastle City Council
Executive, Wednesday 12 November 2008 at 4.00pm

Heart of the City Project

Agreed Executive 2 papers

Executive agreed this item on Wednesday 12 November 2008. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

Executive agreed to: a) Support the lodging of a Stage One Heritage Lottery Fund bid and to the City Council contributing toward the initial 5% of the costs ( it is a requirement of the HLF that the bidder is able to meet 5% of the project costs from their own funds ). This will require a City Council contribution of up to £172,287 over the five year implementation period of the scheme. This will be sourced from existing heritage related revenue budgets over that period. b) look at ways of drawing in further financial backing from either within or outside of the Council to support the project and to undertake and maintain public realm improvements within the Heart of the City area within the lifetime of the project.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Executive

HOC Financial Summary

Item Total (£) Cathedral Cathedral/access (including contingency & inflation) £3,377,682 Contract Works £675,536 Fees £166,569 VAT

Keep Access improvements (including contingency & inflation) A. Capital Works

Contract Works £25,000 Fees £2,200

Black Gate Access improvements / adaptions (including contingency & inflation) Contract Works £841,931 Fees £168,385

Interpretation Conservation & Interpretation works (including fees, contingency, inflation & VAT) £1,079,065

Sub Total of A £6,336,368

Marketing (incl inflation) £27,081 B. Activities

Education (incl inflation) £195,396 Events & Activities (incl inflation) £86,850 Project Management (incl inflation) £245,816

Sub Total of B £555,143 HOC Financial Summary

Total Cost £6,891,511

HLF £3,859,246.00 C. Potential Sources of

One North East / CDC £2,500,000.00 Funding

5% Partnership Contribution £344,575.00 Other Trusts £187,690.00

Total of C £6,891,511

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
12: Heart of the city app1Report 44 KB DownloadRead as text
PDF
Heart of the City ProjectReport 122 KB Download

More from Newcastle Executive

All decisions
MeetingDecisionOutcome
21 Feb 2011 2011/12 Budget, Council Tax and Corporate PlanExecutive agreed to : forward this report and appendices (as amended by Executive at the meeting and the confirmed le... Agreed Open
21 Feb 2011 2011/12 Capital ProgrammeExecutive agreed to:- (i) Note the economic update set out at Appendix A; (ii) Agree the base capital programme for 2... Agreed Open
21 Feb 2011 Newcastle FundExecutive agreed to: (i) note the process for determining the recommended allocation of Council grant aid through the... Agreed Open
26 Jan 2011 The Health of the Ex-Service Community - North East Regional Scrutiny ReviewExecutive Agreed to:- a) welcome the scrutiny report; b) agree to assess the recommendations made to local government... Agreed Open
26 Jan 2011 Financial IssuesExecutive agreed to : (i) Note the latest level of capital programme and approve the inclusion of the new schemes and... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies