Item13
Resolved
Executive agreed to: a) note the increased capital costs associated with the delivery of the scheme; b) approve the revised funding required to deliver the scheme, including the use of a combination of future ring-fenced capital receipts and Regeneration Fund as detailed in section 6.1 of this report; c) the removal of the barrage funding element of the Ouseburn Developer Contribution Model (ORIS) and to inform Planning & Transport Strategy Committee and Development Control Committee accordingly d) approve a revenue budget of up to £0.094m per annum to cover the maintenance and monitoring obligations associated with the operation of the barrage. Funding to be draw down from corporate funds in the first three years of operation (2009-10 – 2011/12) based on evidence of actual spending and subsequently from Environment and Regeneration Directorate’s revenue budget.
Word for word from the decision Newcastle published for this meeting.
Source: democracy.newcastle.gov.uk