Procurement Committee agreed to i) Note the content of the report ii) Give approval for a procurement exercise to be carried out to secure a materials Recovery Service and agree that the procurement can be carried out in partnership with North Tyneside Council; and iii) Authorise the Director of Neighbourhood Services to award the contract and liaise with the Head of Efficiency & Procurement in association with the Head of Commercial Law to complete the necessary documentation
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
1.1This report sets out a request to procure External Professional Services for the appointment of a Materials Recovery Facility Service. The Council’s Financial Regulations require Procurement Committee approval before procuring a contract for external professional services over £50k.
1.2The procurement of a Materials Recovery Facility Service is required to sort, store and onward transport dry recyclable materials collected by the Council’s ‘Blue Bin Service’.
Recommendations
2.1Procurement Committee is recommended to:
1. Note the content of the report;
2. Give approval for a procurement exercise to be carried out to secure a Materials Recovery Service and agree that the procurement can be carried out in partnership with North Tyneside Council; and
3. Authorise the Director of Neighbourhood Services to award the contract and liaise with the Head of Efficiency & Procurement in association with the Head of Commercial Law to complete the necessary documentation. 3. Introduction and background
3.1The procurement of a Materials Recovery Facility Service was agreed by Executive in September 2007 as part of their new integrated recycling and waste collection service.
3.2The procurement was in partnership with North Tyneside Council and resulted in the award of a joint contract with G O’Brien and Sons. The contract commenced in June 2008 and was for a period of 3 years with the option to extend for a further 2 years.
4. Current position and proposals
4.1The current contract will terminate in June 2011 unless the Council takes up the option to extend for a further 2 years.
4.2The service provided to date by O’Brien’s has been very good. They are efficient in receiving, bulking and sending to market the materials they have received from the Council. Their success was recently recognised with a Waste Industry Award for the quality of their work.
4.3Whilst the arrangements in place are working well, it is proposed not to take up the 2 year extension option as outlined in section 5.
It is therefore recommended that a further procurement exercise be carried out in Partnership with North Tyneside Council.
Reasons for the decision
5.1Intelligence gathered during the course of the current year confirms an increase in the market place providers for this service.
5.2Any reduced rates from the procurement exercise will contribute to the Council’s budget savings target and will improve the overall value for money position for this service area.
Alternative options
The alternative option is to extend the existing contract by 2 years. This will provide continuity of service, but will not allow competitiveness. 7. Corporate implications
7.1Financial
The procurement will seek to identify whether there is an opportunity to reduce the Council’s costs in this area.
7.1.1 Any additional comments from the City Treasurer
The Director of Finance and Resources notes the content of the report and that a more competitive rate is being pursued for Materials Recovery. There are, as yet, no financial implications to comment on.
7.2Legal
The Head of Commercial Law has been consulted and has no comments to add.
7.3Strategic Procurement
The Council’s Financial Regulations require Procurement Committee approval for external professional services over £50K. The Corporate Procurement Team is being engaged and consulted and is satisfied that the procurement will be undertaken in the best interest of the Council and will be undertaken in accordance with the Council’s Procurement Procedure Rules.
7.4Consultation and scrutiny
The relevant Scrutiny Committee is Managing Environmental Impact Overview and Scrutiny Panel. The panel has not been consulted to date. Consultation has taken place with the relevant Portfolio Holder.
Risk management
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Playgroup and Nursery ProvisionRESOLVED – That Procurement agreed to: ( i ) Authorise the commencement of retrospective contract negotiations with i...
Regional Legal Services Framework PanelRESOLVED – That Procurement agreed to: ( i ) Approve a collaborative procurement exercise to put in place a 4 year Fr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.