Resolved

Executive agreed to: (i) Approve the Newcastle Accessible Bus Network from 27 March 2011, as set out in Appendix A. (ii) Note the outcome of the consultation process undertaken by Nexus alongside Transport Policy Officers at Newcastle City Council, with regards to network design, timetables, and branding of subsidised services to increase public recognition.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Executive

Portfolio: Environment Sustainability and Transport

Executive 26 January 2011

Accessible Bus Network Development

Report by: Executive Director of Environment and Regeneration

Ward Implications: All For Decision

1. Purpose of the report 1.1 To seek Executive’s approval for the planned changes to the secured services element of the Newcastle bus network. This report gives a high-level summary of the proposals for the Accessible Bus Network, the process that was undertaken during 2010 for consulting on the network, a summary of feedback received and the key issues. It outlines the network design based on the outcome of the consultation.

The Integrated Transport Authority has authorised that Nexus undertake this work on its behalf, together with the Tyne and Wear Authorities. The Council has worked alongside Nexus in determining what the preferred options are in terms of network development. Executive is asked to approve the resulting network design. The implementation date for the revised network is 27 March 2011.

2. Recommendations 2.1 Executive is recommended to:

- Approve the Newcastle Accessible Bus Network from 27 March 2011, as set out in Appendix A.

- Note the outcome of the consultation process undertaken by Nexus alongside Transport Policy Officers at Newcastle City Council, with regards to network design, timetables, and branding of subsidised services to increase public recognition.

Page 1 04/01/2011 3. Introduction and background 3.1 The Accessible Bus Network Design Project was set up in 2009 with the objective ‘to design an accessible bus network for Tyne and Wear that delivers the best possible accessibility for local residents within the funding available, and assists in the achievement of the accessibility targets contained within the Bus Strategy’ The design involved liaison with officers from Nexus, Newcastle City Council, Stagecoach, Arriva and Go North East. Around 90% of all buses in Tyne and Wear are operated as ‘commercial’ services, where the routes and frequencies are decided by the bus operators. The remaining 10% are secured by Nexus using money provided by the councils in Tyne and Wear. Nexus can pay for the whole of a route or just part of it. It can also pay for a route at certain times of day (often early mornings, evenings and Sundays) when there are fewer passengers but the route fills an important social need. This consultation concentrated on all secured services and the changes we propose for them. Appendix A details all of the changes, and Appendix B (to be distributed at the meeting) gives a map showing the proposed new secured bus network for Newcastle upon Tyne.

3.2The key changes proposed for Newcastle relate to enhancing a number of routes and increasing off-peak services, with funding re-directed from the withdrawal of a small number of poorly-used services.

The ‘Link Up’ (Demand Responsive Service) will be withdrawn, as the subsidy per passenger mile is particularly high, at £11.18 per passenger journey in June 2010, which is not perceived to offer value for money in the current economic climate - and the resource previously allocated to this service will be re-allocated to additional and new fully accessible 'fixed-route' service provision, to continue to enable users to meet their accessibility needs. All users of this service have been contacted by Nexus individually to discuss suitable alternatives.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Accessible Bus Network DevelopmentReport 328 KB DownloadRead as text
PDF
Appx Bus networkReport 56 KB Download

More from Newcastle Executive

All decisions
MeetingDecisionOutcome
21 Feb 2011 2011/12 Budget, Council Tax and Corporate PlanExecutive agreed to : forward this report and appendices (as amended by Executive at the meeting and the confirmed le... Agreed Open
21 Feb 2011 2011/12 Capital ProgrammeExecutive agreed to:- (i) Note the economic update set out at Appendix A; (ii) Agree the base capital programme for 2... Agreed Open
21 Feb 2011 Newcastle FundExecutive agreed to: (i) note the process for determining the recommended allocation of Council grant aid through the... Agreed Open
26 Jan 2011 The Health of the Ex-Service Community - North East Regional Scrutiny ReviewExecutive Agreed to:- a) welcome the scrutiny report; b) agree to assess the recommendations made to local government... Agreed Open
26 Jan 2011 Financial IssuesExecutive agreed to : (i) Note the latest level of capital programme and approve the inclusion of the new schemes and... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies