Newcastle City Council
Procurement Committee, Monday 7 March 2011 at 3.30pm

Municipal Waste Management

Agreed Committee 1 paper

Procurement Committee agreed this item on Monday 7 March 2011. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Procurement Committee agreed to: i) Approve the proposal to terminate the current residual waste procurement project. ii) Authorise the Director of Neighbourhood Services in conjunction with the Head of Efficiency and Procurement and Head of Commercial Law to liaise with SITA to agree and finalise the necessary amendments to the current waste management contract as set out in this report. These revised arrangements will then continue until the end of the contract in 2024. iii) Undertake further procurement by 2016 for waste currently being sent to Energy from Waste facility in Teeside with all optional technologies to be considered iv) Review targets once the contract for SRF is in place to ensure these remain challenged.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Procurement Committee

Purpose of the report

1.1This report seeks approval to cease the current residual waste procurement project and as an alternative vary the existing long term Waste Management Contract in place between the Council and SITA. The report sets out the full background of the proposal in the context of the Council’s overarching waste strategy and its longer term objectives and aspirations.

Recommendations

2.1Procurement Committee is recommended to:

1. Approve the proposal to terminate the current residual waste procurement project.

2. Authorise the Director of Neighbourhood Services in conjunction with the Head of Efficiency and Procurement and Head of Commercial Law to liaise with SITA to agree and finalise the necessary amendments to the current waste management contract as set out in this report. These revised arrangements will then continue until the end of the contract in 2024.

1 3. Introduction and background

3.1The Council’s Municipal Waste Management Strategy was agreed by Executive at its meeting in September 2007. This was developed with the aim of moving towards the long term aspiration of achieving zero waste.

In seeking to achieve this aspiration whilst at the same time responding to the challenges of the landfill directive the Council agreed the following targets:

• 5% reduction and re-use of household waste by 2010

• 15% reduction and re-use of household waste by 2020

• 43% recycling and composting of household waste by 2010

• At least 55% recycling and composting of household waste by 2020

• 43% recovery of municipal waste by 2010

• At least 75% recovery of municipal waste by 2020

3.2The strategy in the first instance concentrated on improving front end waste and recycling collection services and the majority of these arrangements are now in place. As a consequence recycling/composting rates in the City have increased from 10% in 2003/4 to 46% in 2009/10. Overall performance during the current financial year will reduce as a consequence of the upgrading of the SITA mechanical biological treatment (MBT) facilities at Byker/Ellington. On these works being completed (March 2011) it is anticipated that recycling and composting rates will return to their 2009/10 levels in subsequent years.

4. Current position

4.1The measures now in place even following the MBT facility upgrade will not be sufficient to protect the Council from future increases in landfill tax and the potential negative impact of the Landfill Allowance Trading Scheme (LATS). To deal with its requirements under LATS and to reduce the risk of further significant increases in landfill tax the Council must now take further measures to deal with the circa 90,000 tonnes of residual waste remaining after all current recycling and composting has taken place.

4.2Council Executive agreed in June 2009 to undertake a procurement exercise designed to assess potential acceptable residual waste technology solutions. Since then, detailed work has been undertaken in assessing both potential technologies and market capacity and capability. In addition the necessary legal, planning and environmental consequences associated with the procurement have also been fully considered. Following agreement by Procurement Committee, the Council has been supported in this process by an Environmental Consultant who has ensured officers have been in receipt of the necessary independent waste expertise which in itself fully reflects national and international developments. Furthermore, as it was always recognised that the procurement and subsequent commissioning of a long

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Municipal Waste ManagementReport 603 KB DownloadRead as text

At this meeting

Whole meeting
4Municipal Waste ManagementThis decision

On this subject at Newcastle

Search all
  1. Municipal Waste ManagementThis decision
  2. Municipal Waste Management - Residual Waste TreatmentDecided
  3. Municipal Waste Management - Residual Waste TreatmentAgreed

More from Newcastle Procurement Committee

All decisions
MeetingDecisionOutcome
17 Mar 2014 Playgroup and Nursery ProvisionRESOLVED – That Procurement agreed to: ( i ) Authorise the commencement of retrospective contract negotiations with i... Agreed Open
17 Mar 2014 Regional Legal Services Framework PanelRESOLVED – That Procurement agreed to: ( i ) Approve a collaborative procurement exercise to put in place a 4 year Fr... Agreed Open
20 Jan 2014 Crisis Response - Homelessness PreventionProcurement Committee agreed to note that: 1. The Chair of Procurement Committee approved the procurement of 8 contra... Agreed Open
20 Jan 2014 Child and Adolescent Mental Health Services (CAMHS)Procurement Committee agreed: 1. To authorise the Assistant Director Children's Social Care, to enter into negotiatio... Agreed Open
20 Jan 2014 Bailiff ServicesProcurement Committee agreed to: 1. Approve the procurement of a Framework Agreement for Bailiff and Debt Collection ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies