Resolved

Procurement Committee agreed to: 1) Agree the appointment of Children North East to act as Youth Council Co-Coordinator for a period of 2 years with an option of a further 12 months subject to funding availability; 2) Authorise the Director of Strategic Partnerships for Children’s Services to award the contract in consultation with the Head of Efficiency & Procurement and the relevant Cabinet and deputy Cabinet portfolio member(s); and 3) Authorise the Head of Efficiency & Procurement in conjunction with the Head of Commercial Law to complete the necessary documentation.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Procurement Committee

Purpose of the report

1.1This report sets out a request to Procurement Committee for approval to negotiate a contract with Children North East to provide the support required to enable the Youth Council to operate effectively over the next two-years and to secure alternative sources of funding for the longer term.

The value of the contract is £80,000 for 2 years (£40,000 in 2012-13 and £40,000 in 2013-14) with an option to extend for a further 12 months subject to funding availability.

1.2The Council’s Financial Regulations require Procurement Committee approval before procuring a contract for external professional services over £50,000.

Recommendations

2.1Procurement Committee is recommended to:

1. Agree the appointment of Children North East to act as Youth Council Co-Coordinator for a period of 2 years with an option of a further 12 months subject to funding availability;

2. Authorise the Director of Strategic Partnerships for Children’s Services to award the contract in consultation with the Head of Efficiency & Procurement and the relevant Cabinet and deputy Cabinet portfolio member(s); and

3. Authorise the Head of Efficiency & Procurement in conjunction with the Head of Commercial Law to complete the necessary documentation. 3. Introduction and background

3.1A contract was awarded to Children North East in February 2010 to establish a Youth Council at the request of the Council’s Executive. The funding of £26,000 in 2009/10, £50,000 2010/11 and £50,000 2011/12 provided a coordinator to facilitate the creation of the Youth Council, the elections and the development of the youth councilors themselves. The project has undergone a development phase and now requires continued support to enable it to grow and become more self-sufficient. Under the new contract arrangements Children North East will employ a co-ordinator to support the Youth Council, the youth councillors and service the Youth Council Steering Group.

3.2It is expected that the Youth Council will have an increased profile, achieve results from its campaigns, make a significant impact and become an integral part of the democratic landscape within Newcastle. It is one important way that young people can exercise their rights and actively participate in the life of the city.

4. Current position and proposals

4.1The current contract expires on 28 February 2012 and in order to build on the last 2 years of development a further contract is required. It is expected by 2014 that the Youth Council will have secured other sources of funding.

4.2The Youth Council considered a number of options open to them beyond the end of this contract, but voted overwhelmingly to maintain their working relationships with Children North East at their meeting in September 2011.

4.3The proposed procurement route is to undertake a negotiated procurement for a period of 2 years with an option of a further 12 months subject to funding availability.

4.4The option of undertaking a competitive procurement has been considered and rejected. The prospect of a new organisation working with the Youth Council would not be a progressive solution as the time they would need to familiarise themselves with the work and build relationships with the 26 youth councillors and other key stakeholders would lead to a loss of momentum. The Youth Council are eager to maintain the momentum and wish to do more to raise their profile, have an impact and be seen as a credible body representing the views of young people in the City.

4.5The option of Newcastle City Council providing direct support to the Youth Council was also considered but rejected. The Youth Council felt this would compromise their independence, which is a fundamental principle the City Council and young people wish to protect. 5. Reasons for the decision

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Youth Council CoordinatorReport 230 KB DownloadRead as text

More from Newcastle Procurement Committee

All decisions
MeetingDecisionOutcome
17 Mar 2014 Playgroup and Nursery ProvisionRESOLVED – That Procurement agreed to: ( i ) Authorise the commencement of retrospective contract negotiations with i... Agreed Open
17 Mar 2014 Regional Legal Services Framework PanelRESOLVED – That Procurement agreed to: ( i ) Approve a collaborative procurement exercise to put in place a 4 year Fr... Agreed Open
20 Jan 2014 Crisis Response - Homelessness PreventionProcurement Committee agreed to note that: 1. The Chair of Procurement Committee approved the procurement of 8 contra... Agreed Open
20 Jan 2014 Child and Adolescent Mental Health Services (CAMHS)Procurement Committee agreed: 1. To authorise the Assistant Director Children's Social Care, to enter into negotiatio... Agreed Open
20 Jan 2014 Bailiff ServicesProcurement Committee agreed to: 1. Approve the procurement of a Framework Agreement for Bailiff and Debt Collection ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies