Cabinet agreed to: i. approve that a competitive procurement exercise is carried out, to put in place a new 4 year (2 years plus 1 x 24 month option to extend) Framework Agreement for External Professional Property Services; ii. authorise the Director of Investment and Development to award the Framework Agreement in consultation with the Assistant Director Commissioning and Procurement and the relevant Cabinet and Deputy Cabinet portfolio member(s); and iii. authorise the Assistant Director, Commissioning and Procurement, in conjunction with the Assistant Director Legal Services, to complete the necessary documentation.
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
Property Services External Professional Framework Partners
Name of Cabinet Member Councillor Ged Bell
Director presenting this report Tom Warburton Director of Investment and Development
Report author Paul Scaplehorn Strategic Property
Report summary Property Services have utilised the services of external property professionals on a Framework Agreement since 2010, to be able to access specialist property advice for specific property projects or areas of work and operational property management when the in house team require additional capacity. This proposal seeks approval to carry out a competitive procurement process to put new Framework arrangements in place.
As the Framework Agreement relates to External Professional Services over £250,000, Financial Regulation 8 and the Procurement Procedure Rules state that we must seek approval from Cabinet in order to proceed.
Summary of decisions being asked for This report sets out a request to appoint External Professional Services onto a Framework Agreement as set out in section 2.1 of this report, to support Property Services (Strategic Property, Property Portfolio (Communities) and Investment and Development). Cabinet report 28 January 2015
1. What is this report about?
1.1In 2010 Property Services established a Framework Agreement of external property advisors to support them in two areas, specialist property advice (three contractors) and operational property management (two contractors). This followed on from a similar arrangement entered into in 2007. The current contract expired on 31 October 2014 and we have put in place interim arrangements until 31 May 2015 to allow time for a competitive EU procurement exercise to be carried out. The Framework Agreement will have two Lots as detailed below: • Lot 1 - specialist property advice which includes areas such as option appraisals and feasibility studies; and • Lot 2 - operational property management covering lease renewals, acquisition and disposal work.
1.2The previous contractual arrangements have successfully provided additional expertise and capacity in a number of areas. For example the specialist advice contract has been used to provide experience and expertise in relation to major property projects such as Stephenson Quarter. In the past the property management element has provided a wide variety of work varying in scope and size including valuations, rent reviews and lease renewals to supplement internal resources, and where independent or specialist valuation advice is required. The table below illustrates the value of contracts placed over the last three years. In many cases contractors costs are recovered from relevant project budgets with the agreement of the Project Director:
2011/12 2012/13 2013/14
Total £82,401 £213,714 £26,517
2. What decisions are being asked for? 2.1 Cabinet is recommended to:
1) Approve that a competitive procurement exercise is carried out, to put in place a new 4 year (2 years plus 1 x 24 month option to extend) Framework Agreement for External Professional Property Services;
2) Authorise the Director of Investment and Development to award the Framework Agreement in consultation with the Assistant Director Commissioning and Procurement and the relevant Cabinet and Deputy Cabinet portfolio member(s); and
3) Authorise the Assistant Director, Commissioning and Procurement, in conjunction with the Assistant Director of Legal Services, to complete the necessary documentation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.