Cabinet: i. Approved the setting up of a Joint Venture Company and gave delegated authority to the Assistant Director of Legal Services to complete the necessary legal documentation in consultation with the Cabinet Portfolio holder. ii. Gave delegated authority to the Director of Public Health to procure a contractor to construct both Parklife hubs and award a contract to appoint a leisure operator to manage the facilities in conjunction with the Assistant Director Inclusion, Commissioning and Procurement and in consultation with the relevant Cabinet Portfolio Holder. iii. Authorised the Assistant Director Inclusion, Commissioning and Procurement in conjunction with the Assistant Director of Legal Services to complete the necessary documentation for the above contracts. iv. Authorised the Acting Director of Place and Assistant Director Legal Services to negotiate and complete lease terms for both sites. v. Approved the inclusion of Newcastle’s Parklife proposal into the capital programme, following submission to the Football Foundation to secure the funding agreement.
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
Parklife Hub Development Name of Cabinet Member: Councillor Kim McGuinness
Director presenting report: Eugene Milne, Director of Public Health
Report Author: Su Cumming, Leisure Specialist
Confidential /Not for publication: Key Decision Appendix 2 – Financial Summary and Appendix 3 Business Viability Model are confidential
Report summary: Providing high quality sports & leisure provision for young people is essential to our healthy city ambition and our ambition to be a Unicef child friendly city. Working with partners the Council has been accepted onto the FA’s Parklife Programme. Parklife is a capital project aiming to improve football facilities in local authority areas, developing modern outdoor facilities that allow games to be played safely, reduce maintenance pressures, and give an all-round high-quality experience for everyone.
Summary of decisions being asked: Cabinet is asked to approve: i. In principle, the establishment of, and transfer of the completed facilities to, a Joint Venture Company (JVC) that will hold the leases of the sites and oversee the appointed management operator; This includes giving the delegated authority for the Assistant Director of Legal Services to complete the necessary legal documentation in consultation with the Cabinet Portfolio holder. ii. Delegated authority to appropriate Directors and Portfolio holder to procure a contractor to build the facilities and a commercial leisure operator to manage them. iii. Authorise appropriate directors to negotiate and complete lease terms for both sites. iv. Inclusion of Newcastle’s Parklife proposal into the capital programme following submission to the Football Foundation to secure the funding agreement. Cabinet report 21 January 2019 1. What is this report about?
1.1This report is to update and seek approval for the City Council with its partners to progress the next stages of the Parklife project in Newcastle in line with the final submission to the Football Foundation.
1.2Newcastle is one of 12 local authorities who will benefit from the available capital investment for Parklife schemes. £250k feasibility funding has already been secured from the Foundation to progress the detailed proposal and business plan. Subject to final approval the Football Foundation will provide 60% of the estimated total project costs of £9-£11m.
1.3Officers have been working with the Football Foundation for 12 months to create a viable business model (appendix 3 (Confidential)). The submission to the Foundation earlier this month set out full estimated capital costs for the development of the two sites which have been identified, Bullocksteads and Blakelaw Recreation Ground (appendix 5). Following procurement of a design team designs for both sites have been commissioned from architects Howarth Lichfield and planning applications are due to be submitted in February/March 2019. Turner & Townsend are providing project management support.
1.4Our submission will also set out the commitment of the City Council and partners to enter into an agreement to establish a Joint Venture Company [“The Newcastle Football Trust”] as required by the Football Foundation. This JVC will be set up as a charity and will take control of the two sites where these facilities will be built by taking a long lease of the land.
1.5The JVC will be responsible for the successful operation of the two facilities. To ensure this happens there is a requirement by the Foundation that the City will procure an experienced leisure operator on behalf of the Newcastle Football Trust, to implement the business plan.
1.6Newcastle City Council will be represented on the JVC Board, along with Newcastle United Foundation, Northumberland Football Association and at least seven independent trustees.
1.7The designs for both the sites are subject to planning permission. The intention is that planning applications will be considered by Planning Committee in April 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.