Resolved
Decision In noting the excellent progress made to date, we requested that the Director of Social Services submit a brief report at our March, 2004 meeting detailing the progress against action plans that were not yet completed.
Overview and Scrutiny Committee decided this item on Tuesday 27 January 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision In noting the excellent progress made to date, we requested that the Director of Social Services submit a brief report at our March, 2004 meeting detailing the progress against action plans that were not yet completed.
1.1The report detailing the findings of the Newham audit against the recommendations of the Inquiry into the Death of Victoria Climbie was presented to the Overview and Scrutiny Committee on 8th July 2003. Copies of the response of the Social Services Inspector were made available to Members of the Overview and Scrutiny Committee.
1.2The Overview and Scrutiny Committee has requested a report concerning the progress against the action plan that was drawn up following the audit.
2. REPORT
2.1The Report of the Inquiry into the Death of Victoria Climbie, also known as the Laming Report, was published in January 2003. Victoria died, aged nine, as a result of appalling abuse and neglect. Her great-aunt and her partner were convicted of Victoria’s murder. The report details some 108 recommendations as follows: • 17 general – largely concerned with the national situation • 46 social care • 27 health • 18 police
2.2Following the publication of the report, the Department of Health compiled audit tools for Social Services, Health Trusts and the Police against some of the recommendations. The Department of Health responded formally to the report within the reen paper on children’s services, entitled “Every Child Matters” presented to Parliament in September 2003. Almost all of the recommendations were accepted in full or in principle.
Overview and Scrutiny Unit, Chief Executive's Department Overview and Scrutiny Committee - 27th January, 2004
2.3The resultant action plan for LB. Newham can be found at appendix 1. Alongside each recommendation is a description of the progress of the action to date. The following actions are not yet complete, though most are in progress: • The production of a service level agreement with the local service centres, the contact centre and the children and families’ front-door teams. This has awaited the new arrangements for CAIT, which are now in place and will be completed next month. • Revision of the process for dealing with form 78s. This awaits the arrival of a new inspector to the Police Child Protection Team and will be completed in January. • The provision of legal advice out-of-hours. This is a requirement for chambers tendering for care proceedings and will be in place early in the New Year. • Revision of induction training. This is included in work to revise the training programme for 2004-5. All new workers received induction but this needs to be fully documented and objectives determined.
SERVICE DELIVERY/PERFORMANCE MANAGEMENT ISSUES
2.4The proposals, as detailed in the action plan, aim to improve services to children in need and children in need of protection. The key issues raised by the audit against the recommendations of the Climbie report have been dealt with by the re-organisation of the CAIT teams and Assessment Service Area, the adoption of the Pan-London procedures and the revision of the Assessment Framework procedures. The senior manager audits now conducted quarterly are indicating areas of weakness, whether of particular workers or teams and remedial action is being taken. The performance information presented to the Mayor, the Cabinet Adviser for Social Services, the Chief Executive and senior managers has been enhanced.
LINK TO VISION AND STRATEGIES
2.5Social Services are one of the key priorities of the Council for 2003- 2004.
LOCAL AREA IMPACT
2.6.. Not applicable.
FINANCIAL AND LEGAL IMPLICATIONS
2.7The Action plan will contained within the cash limit for Social Services for 2003/04 and any ongoing costs will need to be contained within future budgets.
Overview and Scrutiny Unit, Chief Executive's Department Overview and Scrutiny Committee - 27th January, 2004
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UPDATE ON THE PROGRESS OF THE ACTION PLAN FOLLOWING THE AUDIT OF CHILDREN'S SERVICES AGAINST THE RECOMMENDATIONS OF THE INQUIRY INTO THE DEATH OF VICTORIA CLIMBIEReport | 91 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Newham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 May 2025 | Call In of Officer Key Decision: Juniper VenturesOVERVIEW AND SCRUTINY COMMITTEE WEDNESDAY 21 MAY 2025 RESOLUTIONS The following are the resolutions made by the Overv... | Noted | Open |
| 8 May 2025 | Call in of officer key decision - juniper venturesOVERVIEW AND SCRUTINY COMMITTEE THURSDAY 8 MAY 2025 DECISION The following is the decision made by the Overview and S... | Decided | Open |
| 25 Mar 2025 | Welcome and introductionsDecision made by Cabinet on 4 March 2025 on the Development of the Populo Living 2025/26 Business Plan. | Decided | Open |
| 25 Mar 2025 | To consider the extent, if any, to which the public and press are to be excluded from the meetingthat the meeting be held in open session and move into closed session for any discussion of exempt materials. | Decided | Open |
| 25 Mar 2025 | Call In of Cabinet Decision: Populo Living 2025/26OVERVIEW AND SCRUTINY COMMITTEE TUESDAY 25 MARCH 2025 RESOLUTIONS The following are the resolutions made by the Overv... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.