Decision The Mayor agreed, in consultation with the Cabinet Member for Education, to approve the acceptance of the lowest tender from Higgins Construction PLC in the sum of £666,183,00. This decision is subject to the call in process as it was partly based on exempt information.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
1.1The project consists of the construction of a new building comprising a new multi purpose hall refurbishment and improvements to existing accommodation: including providing new WC accommodation at various levels within the existing building, forming a new reception area and sundry external works.
1.2Tenders were invited in November 2003 from five contractors selected from the Borough’s approved tender list. Tenders were received on 9th December 2003 from all five contractors. The lowest tender was received from Higgins Construction PLC in the sum of £747,065.00 This figure was £83,235.00 over the budgeted amount and the Director of Education and Community Learning authorised post-tender negotiations to reduce the tender price. Post-tender negotiations were carried out with Higgins Construction Plc. A review of the specifications achieved a reduction of £80,882.00 giving a revised negotiated tender of £666,183.00.
1.3The tender returns were as follows.
Contractor Tender Sum Higgins Construction PLC £747,065.00 Tenderer B £766,777.00 Tenderer C £779,929.00 Tenderer D £789,504.00 Tenderer E £848,588.00
2 Outline of Proposals
2.1Build a multi purpose hall and link to the existing building and refurbishment and improvements to existing accommodation including new WC accommodation at various levels within the existing building, forming new reception area and sundry external works.
3 Outcomes Sought
3.1To accept the tender in accordance with the Procurement Code of Practice.
2 4 Service Delivery / Performance Management Issues
4.1This project will resolve condition and suitability problems highlighted in the LEA’s Asset Management Plan.
5 Link to Vision and Strategies
5.1The project will make the school building more accessible for pupils and adults with physical difficulties.
6 Local Area Impact
6.1The project will be of direct benefit to pupils attending the school. The Hall will also benefit other members of the community, primarily drawn from the immediate area.
6.2Once completed the improvements will enhance the appearance of the building.
7 Financial and Legal Implications
Legal implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.