Sprowston Mews Forest Gate E7- Appointment of Development Partner

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 23 February 2006. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision The Mayor in Consultation with Cabinet agreed: (i) the appointment of a consortium led by East Thames as the development partner for the Council for the Sprowston Mews project; and (ii) to accept further reports as necessary, including a proposed Collaboration Agreement, between the Council and the consortium. Reasons for Decision In order to progress the Sprowston Mews development project to the next stage. The report and decision have complied with Part 4.2, paragraph 11 of the Constitution. The decision is not subject to the call in process and may be implemented immediately
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report seeks to progress the Sprowston Mews development project to the next stage by seeking agreement to: 1) the appointment of a consortium led by East Thames as a development partner for the Council; 2) accept further reports as necessary, including a proposed Collaboration Agreement between the Council and the consortium

Officer Recommendations

Mayor in Consultation With Cabinet is recommended to agree: 1) the appointment of a consortium led by East Thames as the development partner for the Council for the Sprowston Mews project; 2) to accept further reports as necessary, including a proposed Collaboration Agreement, between the Council and the consortium

Member Consultation

1) General

Although Sprowston Mews is located in Forest Gate North ward, the report has been circulated to Forest Gate North and South Ward Members, as the proposal affects the wider community. The Cabinet Member for Public Realm and Mayoral Advisor on Regeneration have also been asked to comment.

2) Influential Councillor Procedures

This project is a longer-term exercise, and is expected not to be complete until 2010 at the earliest,

1 which will entail a significant amount of consultation at all levels. In order to try to ensure that consultation is comprehensive, but also making the most efficient use of Members’ limited time, the proposed Collaboration Agreement will include a Consultation Strategy. For the present stage, officers are of the opinion that the use of the Influential Councillor procedure is not likely to be the most productive approach, and therefore suggested to Members that it might be better to involve them in more detailed input at a later stage, once the design proposals for the scheme have been drafted, and prior to a planning application being submitted. This part of the is likely to commence later in 2006. Members did not object to this approach when consulted.

3) Overview and Scrutiny

This report was considered by Overview and Scrutiny on December 13th 2005, with a recommendation that officer recommendations be supported.

Reason for the recommendations

In order to progress the Sprowston Mews development project to the next stage.

JOHN TUNNEY INTERIM HEAD OF PHYSICAL REGENERATION AND DEVELOPMENT

Originator of report: Dave Whittaker, Development Projects Group, Physical Regeneration and Development Tel no: E-mail address: 020 8430 2760; [email protected]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report:

1) Report to Mayor in Consultation with Cabinet, March 31st 2005: Sprowston Mews, E7 – Proposed Adoption of Supplementary Planning Guidance 2) Report to Mayor in Consultation with Cabinet, March 31st 2005: Sprowston Mews, E7 – Proposed Search for Development Partner for the Council 3) Sprowston Mews files – with originator of report

Cleared by Finance (officer’s initials) DB Cleared by Legal (officer’s initials) JA Links to Plans and Strategies cleared CH (officer’s initials) Risk Assessment completed KM (officer’s initials) List of enclosures:

None

Executive summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sprowston Mews Forest Gate E7- Appointment of Development PartnerReport 32 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 29 attended
CW
Chris WoodOfficer, present
SR
Sir Robin WalesChair, present
AB
Councillor Andrew BaikieMember, present
CB
Christine BowdenMember, apologies
UD
Councillor Unmesh Desai AMMember, absent
LH
Councillor Lester HudsonMember, present
JL
Councillor Joy Laguda MBEMember, apologies
JL
Councillor June LeitchMember, present
AM
Councillor Anthony McAlmontMember, apologies
QP
Councillor Quintin PeppiattMember, present
AS
Councillor Amarjit SinghMember, absent
PB
Councillor Paul BrickellMayoral Adviser, present

All 29 on the meeting page

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies