Agreed Planning 4 papers

Development Control Committee agreed this item on Wednesday 19 April 2006. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision The Committee agreed: a) agree the reasons for approval and to grant planning permission subject to the following conditions: Conditions: 1. The development to which this permission relates must be commenced not later than the expiration of THREE YEARS from the date of this permission. Reasons: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990. 2. All works are to be completed in accordance with drawing numbers 650/S1A, /S2, /S3, /P10A, /P11B, /12B, /P13B, /P14B, /P15A /P16A.No further drawings apply, unless otherwise approved in writing by the Local Planning Authority. Reason: To ensure that the development is constructed in accordance with the approved drawings, and protect the local amenity with regard to policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001) and policy 4B.1 of the adopted Unitary Development Plan. 3. Prior to the commencement of works on the development hereby permitted, details of materials to be used on all external surfaces of the building hereby approved shall be submitted to and approved by the Local Planning Authority. Details should include colour, texture and type of materials. The approved materials are to be constructed/installed prior to occupation of the development and shall be permanently maintained thereafter. Reasons: To ensure a satisfactory standard of external appearance and protect local amenity and with regard to policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001), and policy EQ19 of the adopted Unitary Development Plan, and policy 4B.1 of the adopted London Plan. 4. Prior to the commencement of any works on the site, a plan showing the proposed Landscaping Scheme shall be submitted to and approved by the Local Planning Authority. The scheme shall include the following: i. Full details of plants and trees (common and Latin names, size and pot height; density or number, tree girth and method of growth i.e. container or open ground). ii. Maintenance schedule iii. Full details of materials to be used on paved areas and other hard surfaces. iv. Suppliers or manufacturers v. Guide to construction vi. Paving/fencing/colours/finishes vii. Location of lighting viii. Any play equipment (specs, manufacturer, British or European Standard) ix. Any features or artworks All planting, seeding or turfing shall be implemented in the first planting season following occupation of the buildings or the substantial completion of the development, whichever is the sooner. Any plants or trees that die or are removed, damaged or diseased within a period of FIVE years from the substantial completion of the development shall be replaced to the satisfaction of the Local Planning Authority in the next ... view the full minutes text for item 11.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Development Control Committee

Summary

1.1The application seeks permission to redevelop a redundant commercial premises in a residential setting. A Victorian building would be converted to accommodate six flats with an attached new build element to provide a further flat and two houses. The remainder of the buildings on the site would be demolished to make way for amenity space and parking. The scheme is considered to represent a high quality and sensitive design solution which would be wholly in keeping with the Victorian terrace street scene. The proposed density is acceptable, each new dwelling would have a dedicated off street parking space, and amenity space provision is of good quality. No material harm would result to neighbours’ amenities. While a number of residents have expressed concern at the impact on parking, Transportation accept provision of one space per unit as acceptable here, and the overall effect of the development will be to significantly enhance the environment.

2. IMPLICATIONS (a) Legal and Financial Members should take account of the provisions of the Human Rights Act 1988 as they relate to the application and conflicting interests of the applicant and any third party opposing the application in reaching their decision.

The provisions of the Act have been taken into account in the processing of the application and the preparation of this report.

(b) Service Delivery none

(c)Equality none

Recommendations

3.1The Committee is asked to:

a) agree the reasons for approval and b) grant planning permission subject to the following conditions:

Conditions:

1. The development to which this permission relates must be commenced not later than the expiration of THREE YEARS from the date of this permission.

Reasons: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990. 2. All works are to be completed in accordance with drawing numbers 650/S1A, /S2, /S3, /P10A, /P11B, /12B, /P13B, /P14B, /P15A /P16A.No further drawings apply, unless otherwise approved in writing by the Local Planning Authority.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24: 34 Sixth Avenue, Manor Park, E12 5PPReport 210 KB DownloadRead as text
PDF
Pictures 001Report 732 KB Download
PDF
Pictures 002Report 861 KB Download
PDF
Pictures 003Report 730 KB Download

At this meeting

Whole meeting

Who was there

7 of 15 attended
CS
Councillor Chris SeddonMember, apologies
RM
Councillor Ron ManleyChair, present
CB
Christine BowdenMember, absent
AC
Councillor Akbar ChaudharyMember, apologies
BC
Councillor Bryan Collier MBEMember, present
IC
Councillor Ian CorbettMember, absent
AG
Councillor Alan GriffithsMember, present
KK
Councillor Khalil Kazi OBEMember, present
SS
Sukhdev Singh MarwayMember, present
CM
Councillor Conor McAuleyMember, present
RA
Councillor Riaz Ahmed MirzaMember, absent
PS
Pat SheekeyMember, absent

All 15 on the meeting page

More from Newham Development Control Committee

All decisions
MeetingDecisionOutcome
3 Mar 2010 370 Romford Road, Forest Gate, London E7 8BSDecision The Committee agreed the reasons for approval as outlined in the report and granted planning permission subj... Agreed Open
3 Mar 2010 120 High Street, E6Decision The Committee agreed to defer consideration to a later meeting. Agreed Open
3 Mar 2010 Dersingham Infant School, Lawrence Avenue, Manor Park E12Decision The Committee agreed the reasons for approval as outlined in the report and granted outline planning permiss... Agreed Open
3 Mar 2010 Eastlea Community Comprehensive School, Exing Road E16Decision The Committee agreed the reasons for approval as outlined in the report and granted full planning permission... Agreed Open
3 Mar 2010 44 The Broadway, E15Decision The Committee agreed the reasons for approval as outlined in the report and granted planning permission subj... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies