Decision The Mayor agreed: 1. the proposed procurement proposal and prices for specialist technical support for the Central Park – Heritage Lottery Fund Restoration Project; 2. in principle that the Council does not carry out a pre-tendering exercise and instead exercises its option under the existing contract with Sprunt to extend the contract to include the final phase of the services; and 3. to delegate the final decision to the Executive Director Resources and the Executive Director Adults, Culture and Community Services to waive the requirement in the Procurement Code of Practice to formally tender and to negotiate and approve the contract. This decision is subject to the call-in process as the decision was based on part exempt information. The call-in period will expire at 5pm on 6 March 2007.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
Is it in the Forward Plan? Yes (date) Date report published 14/02/07
Date of meeting 22/02/07
Subject: Heritage Lottery Fund (HLF) Bid: Central Park - Extension of Services Contract for Specialist Technical Support
Source: Head of Culture
Wards affected: All Wards, but particularly East Ham South, East Ham Central, Wall End and Boleyn
Exempt Information
Appendix A is not for publication as it contains exempt information by virtue of paragraph 3 of the Access to Information Procedure Rules set out in the Constitution pursuant to Schedule 12A Local Government Act 1972, as amended. It is considered to be in the public’s interest to withhold this information as it concerns information which if disclosed is likely to affect the Council’s ability to receive competitive bids in the future. It also contains commercially sensitive information that could dissuade potential bidders for future contracts.
Procurement Code
In line with the requirements of the revised Procurement Code, set out in this report for the Mayor’s information and consideration are details of a proposed future contract extension which is above the European Union thresholds (but less than £500,000) but in line with the option to extend stated within the OJEU notice dated 28.11.05.
The recommendation in this report is to exercise an option in the existing contract to extend the contract to include the next phase of services with the same contractor. Although this would not ordinarily be described as a tender exercise Officers have decided to report this to the Mayor as it could fall within the spirit of the new requirement within the Procurement Code to provide the Mayor with a pre-tender report. It is of course possible to decide not to extend and there might therefore follow a re-tendering exercise. The Procurement Code would also require the Council to carry out a formal tendering exercise for a contract with a value of the proposed extension. Accordingly if it is decided to exercise the option to extend it will be neccessary to waive that part of the Code
In accordance with the Mayoral Scheme of Delegations, it is proposed that the requested approval of the Mayor to accept an extension to the existing contract (instead of re-tendering) to cover the next phase as set out in the recommendations to this report will be passed to the Executive Director Resources and the Executive Director Adults, Culture & Community Services who would otherwise have delegated authority to approve the extension to the contract.
Officer Recommendations
The Mayor is asked to consider the proposed procurement proposals and prices for specialist technical support for the Central Park – Heritage Lottery Fund Restoration Project and agree
1. in principle that the Council does not carry out a pre-tendering exercise and instead exercises its option under the existing contract with Sprunt to extend the contract to include the final phase of the services; and
2. to delegate the final decision to the Executive Director Resources and the Executive Director Adults, Culture and Community Services to waive the requirement in the Procurement Code of Practice to formally tender and to negotiate and approve the contract.
Reasons for Officer Recommendation
Project Value for Money – the proposed consultants submitted the lowest tender price following an EU procurement process in Nov 05. There is no reason to believe that re-tendering would improve value for money.
Project Timeline – re-tendering the contract for specialist technical support would put pressure on the project timeline and result in inflationary pressure on project costs. Project Quality – the proposed consultants have performed to a high standard in all aspects of the contract.
Project Continuity – there are potential continuity issues arising from appointment of any new specialist support.
Member Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.