Resolved
Decision Agreed to note.
Audit Board agreed this item on Wednesday 7 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Agreed to note.
AUDIT BOARD REPORT Date of meeting 7th March 2007 Agenda Item Subject Heading Corporate Risk Register
Is this Item for: Information and Discussion Information or Discussion Summary of The purpose of this paper is to update Audit Board Members on the current status of the Council’s Corporate Risk issues/key points Register. This report will also detail the improvement plan for discussion for the register and discuss how the Risk Management Team will report to Members on the key risks held on the system. Officer preparing report Ashley Easen Contact 020 8430 4795 Number and e- [email protected] mail address Manager’s name Marianne Manager’s Title Chief Internal Auditor Wood Purpose of this Report The purpose of this report is to inform Members of the Councils Corporate Risk Register – its current status and plan for improvement which is currently being implemented. This report details how the risk management team intend to report to Audit Board on the key risks held on the register.
Background Information A Corporate Risk Register has been in place in the Authority since 2003 through the software providers - JC Applications (JCAD). This system which is called Risk2003 was acquired when risk registers were nationally still in their infancy and in effect Newham was one of the pilot Authorities for this type of system. As a consequence of this, we have benefited in so much as having the system tailored by the providers to meet our changing needs and requirements - identified through forces such as the CPA process and internal restructuring of services. However, being a pilot Authority has also meant that the providers were initially slow to make the necessary changes and this has played a part in the register becoming unmanageable.
Operation and management of a risk register is a constant learning experience for both staff and the risk management team. Officers now have a greater understanding of how to assess the risks they face in delivering their services and the team are more knowledgeable on how to store this information and report on it.
The Risk Register Review In March 2006, the risk team launched a full review of the Corporate Risk Register. At that time the register held in the region of 1700 risks. This was an unmanageable number of risks for the team to be able to extract and report upon and was an unrealistic number for services to review and update regularly.
In consultation with services, the team identified what functions the register needed to provide. This included: • Risk information which is transparent and available when required • A filter to be able to search the data for relevant information • Risks linked to the key business objectives and related to key performance indicators • The ability to produce a variety of reports • To have an audit trail to show when and who amendments have been made by • To have appropriate security functions.
The risk team consulted with stakeholders and undertook a process mapping exercise to establish the desired specification and identify all available options. The resulting decision was to remain with JCAD but acquire a new blank database where the team could build the new structure of the Council themselves and start afresh. This is not to say that all the information held in the full register was obsolete, much of it required only a review and then could be entered onto the new system. The target date to have a revised risk register in place as reported to the Risk Management and Emergency Planning Group (RMEPG) was the end of March 2007 and the team are confident that this will be achieved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk RegisterReport | 18 KB | DownloadRead as text |
Follow Audit Board at Newham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Feb 2019 | Minutes, Decision Sheet and Action PlanRESOLVED that: 1. The minutes of the last meeting of the Board, held on 7 November 2018, be approved as a correct rec... | Approved | Open |
| 12 Feb 2019 | Risk Management Policy and StrategyRESOLVED that the , be noted. | Noted | Open |
| 12 Feb 2019 | Annual Treasury Management Strategy StatementRESOLVED that the Annual Treasury Management Strategy Statement, be noted, subject to the reference on Page 50 being ... | Noted | Open |
| 12 Feb 2019 | Duration of MeetingRESOLVED that the meeting be extended until 9.30pm, if required, to enable the remainder of the business to be transa... | Decided | Open |
| 12 Feb 2019 | Exclusion of Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following items of busine... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.