Bed and Breakfast Pre-Tender Report (Proposed procurement above EU threshold) and Interim Provision of Bed and Breakfast Accommodation

Agreed Committee 1 paper

Mayoral Proceedings agreed this item on Thursday 8 March 2007. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Decision The Mayor agreed that: 1. the contract for the provision of Bed and Breakfast accommodation and related services be tendered, following the Council’s corporate procurement policies and procedures, for a contract period of three years; and 2. the Council procures its interim need for bed and breakfast accommodation through the use of spot booking arrangements from suitable providers by applying the Bed and Breakfast Information Exchange (BABIE) rates to ensure value for money. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the call in process and may be implemented immediately
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Background

1.1Bed and Breakfast provision was previously managed by Paddington Churches Housing Association until March 2006 when the London Borough of Newham took over the service.

1.2External consultant investigations into allegations concerning the Council’s temporary accommodation service identified serious weaknesses in the procurement of services in Housing Needs; this exercise is one of the key recommendations.

2. Reasons for outsourcing

2.1The London Borough of Newham can not provide this service internally, and historically this service has been provided under contract with various external agencies. Block-booking contracts with previous providers of bed and breakfast accommodation were brought to an end on 13 February 2007.

3. Potential use of proposed contract over life of contract

3.1Provision of Bed and Breakfast accommodation for homeless households.

4. Estimated value of the proposed procurement over the life of the proposed contract

4.1The estimated value for the Bed and Breakfast contract for the provision of temporary accommodation for homeless households is £5 million per financial year and the contract period will be for a maximum three-year period. Part of our of the strategy for reducing the number of families in temporary accommodation and meeting the government target is to direct customers to the private sector before they become homeless. This will thus reduce the overall demand for bed and breakfast and the associated expenditure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bed and Breakfast Pre-Tender Report (Proposed procurement above EU threshold) and Interim Provision of Bed and Breakfast AccommodationReport 18 KB DownloadRead as text

At this meeting

Whole meeting
2Major Road Open Space – Appropriation of landOn the agenda
3Bed and Breakfast Pre-Tender Report (Proposed procurement above EU threshold) and Interim Provision of Bed and Breakfast AccommodationThis decision

Who was there

5 of 5 attended
SR
Sir Robin WalesChair, present
AB
Councillor Andrew BaikieMember, present
IC
Councillor Ian CorbettMember, present
RC
Councillor Richard CrawfordMember, present
UD
Councillor Unmesh Desai AMMember, present

On this subject at Newham

Search all
  1. Bed and Breakfast Pre-Tender Report (Proposed procurement above EU threshold) and Interim Provision of Bed and Breakfast AccommodationThis decision
  2. Homeless Persons Unit Temporary Accommodation and Bed and Breakfast Rent IncreasesAgreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open