Resolved
Decision The Committee agreed: a) the reasons for approval set out in Para’s 9.1 and 9.2 of this report; and b) to delegate authority to the Planning Services Manager to grant full planning permission for this application subject to the completion of a S.106 legal agreement in accordance with the Heads of Terms set out in para 9.3 of this report and subject to the inclusion of conditions set out in para 2.2 of this report. Summary of Conditions: It is proposed that conditions relating to the following are included with any planning permission granted; 3 year commencement time frame, drawing numbers, construction hours, refuse storage, external materials, landscaping, environmental code, kitchen extract ventilation, sustainable urban drainage, compliance with Lifetime Homes, a scheme of archaeological investigation, a parking management plan, a contaminated land investigation, road traffic survey and mitigation, sound insulation and an air quality report.