Decision We: (i) Requested that Housing and Public Protection and Newham Homes officers submit a progress report at our July, 2009 meeting detailing: · Management actions being taken to reduce further any overruns of contracts · Value for money, quality and improved customer service standards · Comparative data on value for money, quality and customer service for London Boroughs
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
Source: Paul Munday, Interim Property Services Director, Newham Homes Kevin Hagger, Head of Design Services, LB Newham
1. Introduction
1.1Newham Homes officers reported to Overview and Scrutiny Committee on 24 June 2008 on the processes impacting on both tenants and leaseholders that are involved in delivering major refurbishment work. This included consultation and feedback, value for money, and quality monitoring, and how the process was implemented with respect to the scheme at Sussex Road, East Ham, E6.
1.2Officers were subsequently asked to report further on overruns to contracts, the safeguards in place to minimise them and whether penalty clauses are written into the contracts. In addition officers were asked to report on what quality monitoring systems there are, what consultation processes are in place, and on the complaints procedure and customer service standards.
1.3This report therefore deals in Section 2 with the instances of overruns to major schemes, what safeguards there are and whether there are any penalty clauses within the contract. Section 3 outlines the consultation (both general consultation and specific, statutory consultation with leaseholders required for recharging), Section 4 covers how quality is controlled and delivered on site, including the how residents can raise concerns. Section 5 explains how quality and resident satisfaction is monitored over the whole programme.
2. Overruns to Major Schemes
2.1Overruns of Projects
In answer to the question ‘is it normal for projects to overrun’, while not normal, unfortunately they sometimes do, particularly when working on existing buildings with many unknowns. Details of major refurbishment projects over £500k which Newham Homes has started on site since it was formed in December 2005 are shown in Appendix 1. Of the 23 projects completed, 12 have overrun, which equates to 52% of the total projects. The reasons for overruns are varied and often can not be attributed to any particular parties’ fault. For instance, contractors have experienced a project where a flat caught fire damaging the scaffolding, they have found asbestos hidden behind timber panels; and they have encountered stores where it was intended to run new electrical rising mains mistakenly having been transferred to a leaseholder who attempted to hold Newham Homes ‘to ransom’.
However, the majority of overruns included within this report involve increased work to the project. This is mainly due to the refinement of priorities between the typical historical brief and the brief required to deliver the Modern Homes programme.
Now that Newham Homes have settled on their requirements for each project there has been a significant reduction in the number of projects exceeding their programmes.
Construction projects are always ‘high risk’ activities due to the numerous unknowns, from the weather to labour shortages to hidden services/asbestos. However, as previously reported Newham Homes has now adopted ‘Partnering’ as its main method of procurement and delivery of refurbishment schemes, whereby long term relationships with contractors encourage continuous improvement in quality, cost and time savings. One of the objectives of ‘partnering’ is to reduce the unknowns through familiarity, and therefore reduce the risks. It is recognised that it important to minimise overruns, which is why in Newham Homes’ partnering frameworks they are monitored as a standard KPI (Key Performance Indicator) on a monthly basis.
While it is not realistic to expect overruns to be completely eliminated Appendix 1 does show clearly that the change to partnering arrangements has considerably improved the situation, with only one of the eleven completed partnering projects overrunning.
2.2Penalty Clauses
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.