Registered Social Landlord - Additional Preferred Partner Tender Process

Agreed Committee 1 paper

Mayoral Proceedings agreed this item on Thursday 5 February 2009. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Decision The Mayor agreed: 1. to approve the principle of recruiting new preferred partners; and 2. that the existing partners should remain in place until 2013. Reasons for the Decision To facilitate the ongoing development of housing and affordable housing within the borough. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

To seek permission from the Mayor to advertise for and recruit new preferred Registered Social Landlord development partners for the borough. The report sets out the reasons for seeking additional partners and the process that will be undertaken.

It explains why existing partners and the new ones recruited should remain in place until 2013.

Recommendations

The Mayor is asked to:

1. Approve the principle of recruiting new preferred partners; and

2. Agree that the existing partners should remain in place until 2013

Reasons for the recommendations

To facilitate the ongoing development of housing and affordable housing within the borough.

Consultation

Councillor Andrew Baikie, Executive Member for Housing, Process and Business Efficiency has read and amended the report. NAME OF LEAD OFFICER: Debbie Dinsdale POSITION: Interim Head of Housing and Public Protection

Originator of report: Fred Nugent Tel no: 020-84305469 E-mail address: [email protected]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report: • Preferred Partners Report to Mayoral Proceedings 26 July 2007

List of enclosures / Appendices: • None Report

1. Introduction and Background

1.1On 26 July 2007 at a meeting of Mayoral Proceedings, it was agreed that the council should recruit new Registered Social Landlord (RSL) preferred development partners to deliver affordable housing in the borough. This process was completed in January 2008 with the approval of eight partners.

1.2At this time, eight partners was viewed as an adequate number to ensure the quantity and quality of housing being developed could be well managed and regulated in partnership with Newham.

2. Key Considerations and Sustainability

2.1The “credit crunch” has led to the largest developments in the borough being delayed and the potential new supply of affordable housing being seriously reduced.

2.2To address this issue we wish to recruit new RSL development partners who will take the lead in purchasing land and developing housing without recourse to section 106 agreements with private developers. This will bring new resources and investment to ensure a supply of housing both private and affordable is maintained. The current economic climate has will lead to a greater focus on public sector led regeneration and housing developments. The new RSL partners will be selected against identical criteria to those, which were used for the previous selection.

2.3To ensure continuing and new investment in the borough we wish to guarantee the status of our preferred partners up to 2013, this will give them impetus to invest, plan and develop based on a medium to long-term strategy.

3. Service Delivery and Performance Issues

3.1This proposal will improve the likelihood of public sector led regeneration and housing development in the borough while bringing private sector investment. It will increase the possibility of delivering more housing across all tenures.

4. Links to Community, Local Area Agreement, Corporate Strategies and any other relevant Plans or Strategies

4.1This report continues the work of the RSL Preferred Partners reaffirmed in July 2008. 5. Risk Management

5.11. The supply of housing and affordable housing may be severely curtailed without the input of new investment both private and public.

2. Without additional partners we will be totally dependent on a reversal in current market sentiment to deliver housing.

6. Impacts

6.1Equalities/Diversity implications

6.1.1 the recruiting of additional partners will increase the possibility of providing more affordable housing in the borough. This will disproportionally help those from BME backgrounds who make up the majority of those on the housing waiting list.

6.2Protecting Children

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Registered Social Landlord: Additional Preferred Partner Tender ProcessReport 16 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 5 attended
SR
Sir Robin WalesChair, present
AS
Councillor Amarjit SinghMember, apologies
CB
Christine BowdenMember, apologies
AK
Councillor Alec KellawayMember, apologies
RA
Councillor Riaz Ahmed MirzaMember, apologies

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies