Brooks Road Area - Procurement of a Building Contractor

Agreed Committee 1 paper

Mayoral Proceedings agreed this item on Thursday 19 February 2009. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Decision The Mayor agreed that the contract for the refurbishment of low rise properties on the Brooks Estate be awarded to Frencon Construction Ltd. Reasons for the Decision The refurbishment of the low-rise properties is part of the on-going works on the Brooks Estate. This phase will enable the Council to complete the enveloping works and major external upgrade of the building in the context of the wider regeneration of the estate. This decision is subject to the call-in process as the decision was based on part exempt information. The call-in period will expire at 5pm on 6 March 2009.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

The report seeks approval to award the contract for the external refurbishment of low- rise properties at Pelly Road, Stratford Road and Fothergill Close. The buildings form part of the Brooks Estate refurbishment project. The report sets out the tendering process undertaken and the evaluation conclusions by officers.

Recommendations

The Mayor is requested to agree that the contract for the refurbishment of low rise properties on the Brooks Estate is awarded to Frencon Construction Ltd.

Reasons for the recommendations

The refurbishment of the low-rise properties is part of the on-going works on the Brooks Estate. This phase will enable the Council to complete the enveloping works and major external upgrade of the building in the context of the wider regeneration of the estate.

Consultation

Cllr Zulfiqar Ali and Plaistow North Members have been consulted regarding the refurbishment plans to the Brooks Road Estate. Cllr Andrew Baikie, Executive Members for Housing, Process and Business Efficiency has also been consulted.

NAME OF LEAD OFFICER: Debbie Dinsdale POSITION: Interim Head of Housing and Public Protection

Originator of report: John McCollin Tel no: 0208 430 6262 E-mail address: [email protected]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report:

None

List of enclosures / Appendices: Appendix A (Exempt) Tender Evaluation Process report and scoring matrix Report

1. Introduction and Background

1.1The Mayor has previously received and agreed reports regarding the contract acceptance on the Brooks Estate including the high-rise buildings and other low rise properties. A pre-procurement report was submitted and agreed on 17th September 2008. This report now addresses the final stage to appoint the contractor to carry out the works to the buildings.

1.2The Council’s vision is to bring all dwellings up to the decent homes standard and improve the overall appearance of estate alongside the high quality of built environment already carried out. The local team in conjunction with Ward Members has carried out detailed consultation with residents as well complying with statutory duties to leaseholders.

1.3The competition for the selection of the contractor has been carried out in line with the Council’s Contract Standing Orders. In total 8 invitations to tender were issued to firms selected from the Council’s Approved list. All tenders were returned and assessed by officers against the published award criteria.

1.4The refurbishment contract will be undertaken under a standard JCT form of contract with the Council’s amendments. The Council, through its design team, has issued full design drawings and requested a method statement addressing the contractors’ approach to resident liaison and programme of works. A priced package and method statement responses have been received from each bidder. This is the tender price, programme and resident liaison arrangements accepted by the Council.

2. Key Considerations and Sustainability

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Brooks Road Area: Procurement of a Building ContractorReport 65 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 19 attended
SR
Sir Robin WalesChair, present
AB
Councillor Andrew BaikieMember, present
CB
Christine BowdenMember, present
PB
Councillor Paul BrickellMember, present
IC
Councillor Ian CorbettMember, apologies
JC
Councillor Jo CorbettMember, apologies
RC
Councillor Richard CrawfordMember, present
UD
Councillor Unmesh Desai AMMember, present
CF
Councillor Clive Furness BEMMember, apologies
LH
Councillor Lester HudsonMember, present
AK
Councillor Alec KellawayMember, apologies
JL
Councillor Joy Laguda MBEMember, present

All 19 on the meeting page

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies