Decision The Mayor agreed that tenders be sought for a second Schedule of Rates Term Contract for Landscape Works and maintenance to run for one year from approximately April 2010 to March 2011. Reason for the Decision The appointment of a further Landscape Works Term Contractor will ensure that the Council’s service can continue to provide efficient project delivery to a high standard with confidence in response to requests from Client service areas to carry out small to medium scale soft and hard landscape works. This will enable the public to access these facilities sooner, thus improving public perception of delivery. A new Schedule of Rates will also provide a useful tool for the compilation of reasonably accurate estimates for Clients to inform funding bids and budgets. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
This report seeks Mayoral approval to seek tenders for a second Landscape Works Term Contract for the period 2010 to 2011 based on a Schedule of Rates submission. This is in order to ensure a high standard of delivery, as well as optimise the use of resources and reduce response times in the delivery of the growing number of small to medium scale landscape and environmental improvement projects.
The Tender Acceptance Report will be submitted to the Mayor in due course for the purposes of appointing a contractor for these works. The Tender Acceptance will be a Key Decision.
The potential value of the Contract over the one-year term is anticipated to be in the region of £1.5m allowing for inflation.
This report was originally considered on 17 December 2009 and deferred for further consultation on Economic Impacts. Councillor Brickell has been consulted and has agreed to advise the Mayor to approve the report with the inclusion of the provisos addressed in italics in section 6.6 of this report (the rest of the report remains unchanged). Recommendation
The Mayor is asked to agree that tenders be sought for a second Schedule of Rates Term Contract for Landscape Works and maintenance to run for one year from approximately April 2010 to March 2011.
Reason for recommendation
To enhance delivery capacity and ensure an efficient value for money service to our Clients and the residents of Newham.
Based on current projects and forecasts, the volume of future landscape works is estimated to be in the region of approximately £1.9m per annum. Approximately £400k of this will be implemented through the current Term Contract (Blakedown) as at present.
The options considered are:
1. To let an additional Landscape Term Contract to run concurrently with the existing Landscape Term Contract (Blakedown); or
2. To carry out a formal tender/quotation process for each project (in line with LBN Contract Standing Orders) that cannot be accommodated within the £400k per annum works limit of the current Term Contract (Blakedown).
The appointment of a further Landscape Works Term Contractor will ensure that our service can continue to provide efficient project delivery to a high standard with confidence in response to requests from Client service areas to carry out small to medium scale soft and hard landscape works. This will enable the public to access these facilities sooner, thus improving public perception of delivery. A new Schedule of Rates will also provide a useful tool for the compilation of reasonably accurate estimates for Clients to inform funding bids and budgets.
Due to the nature of landscape works being characterised by relatively low budgets and short programmes with a requirement to optimise the planting season, it is considered better value for the Council to procure the bulk of works under this type of Term Contract rather than to invite individual tenders or quotations for each job.
This process optimises team resources and shortens the timescale of affected projects between approval and implementation, which is important when considering the restricted planting season (October – March) and the need to meet both financial and delivery targets at the end of the financial year.
Consultation
The following Executive Members have been consulted in the preparation of this report:
• Executive Member for Public Realm, Councillor Ian Corbett. • Executive Member for Olympics and Public Affairs, Councillor Paul Brickell. NAME OF LEAD OFFICER: John Simpson POSITION: Divisional Director: Highways, Transport and Parking
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.