Decision The Mayor: 1. Approved the design and materials to be used on the Scheme for Section 1 ( Plashet Grove to Ron Leighton Way) and Section 2 (Ron Leighton Way to Barking Road) subject to regular reporting back on performance measures, value for money and officers ensuring the Contractor was aware of the concerns expressed; 2. Noted the procurement process and approve the appointment of the contractor to undertake the works; 3. Approved the budget allocation for the scheme of £3560k; 4. Approved the proposed works programme, to commence in April 2011 and be completed by August 2011; 5. Noted the proposed public communications to be undertaken for the scheme; and 6. Delegated power to the Divisional Director Highways, Transport & Parking to approve the detailed design for implementation of the scheme, in consultation with the Executive Member Environment & Infrastructure and the Member Reference Board. Reasons for the Decision To ensure delivery of this high profile scheme within budget and programme, whilst delivering a high quality and value for money finished product. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
This report sets out the proposal to take forward the East Ham Town Centre scheme with highway and streetscape works to commence in April 2011 and proposed to be completed by August 2011. The works will include the renewal of footways and carriageway along High Street North, between Plashet Grove and Barking Road, together with the removal of clutter.
A request has been made to the Chair of Overview and Scrutiny that the decision is made exempt from call-in.
Reasons for Lateness
The report was not available at the time of the despatch because it was anticipated that the report was to be published in time for an additional later meeting proposed for the 21st February 2011. Reasons for Urgency
The decisions cannot wait until the next scheduled meeting because they are needed in order to progress the scheme through to the start date on site of 4th April 2011.
Recommendations
The Mayor is recommended to:
1. Approve the design and materials to be used on the East Ham Town Centre Scheme for Section 1 (Plashet Grove to Ron Leighton Way) and Section 2 (Ron Leighton Way to Barking Road). 2. Note the procurement process and approve the appointment of the contractor to undertake the works. 3. Approve the budget allocation for the scheme of £3560k. 4. Approve the proposed works programme, to commence in April 2011 and be completed by August 2011. 5. Note the proposed public communications to be undertaken for the scheme. 6. Delegate power to the Divisional Director Highways, Transport & Parking to approve the detailed design for implementation of the scheme, in consultation with the Executive Member Environment & Infrastructure and the Member Reference Board.
Reasons for the recommendations
To ensure delivery of this high profile scheme within budget and programme, whilst delivering a high quality and value for money finished product.
NAME OF LEAD OFFICER: John Biden POSITION: Head of Traffic & Transportation
Originator of report: Mick Hepworth Tel no: 020 3373 1064 E-mail address: [email protected]
Local Government (Access to Information) Act 1985 Background papers used in preparing this report: • Report to Cabinet 16th Sept 2010 (Revised Local Implementation Plan 2010/11) • Report to Cabinet 21st October 2010 (Local Implementation Plan 2011/11 and 2011/12).
List of enclosures / Appendices: • Appendix A – Scheme Aims – in Part B • Appendix B – Scheme Materials • Appendix C – Scheme Programme • Appendix D – Contractor Procurement Report - Part A
1. Introduction and Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.