London Borough of Newham
Mayoral Proceedings, Thursday 24 January 2013

Atherton Leisure Centre - Advance Works Building Contract

Agreed Committee 2 papers

Mayoral Proceedings agreed this item on Thursday 24 January 2013. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

Decision The Mayor agreed to: 1. approve the development of a package of enabling works in advance of the main works contract to maintain the proposed project programme. The Advance Works contract will comprise: · Demolition and asbestos surveys · Asbestos removal · Ground investigation works · Soft strip out of the existing building; and 2. delegate authority to the Chief Executive in consultation with the Director - Strategic Regeneration Planning and Olympic Legacy, the Director - Business Systems, Property and Commercial Development, the Director - Legal, People and Change and the Executive Members for Housing and Customer Services, Infrastructure and Environment, Regeneration and Strategic Planning to finalise the programme of advance works. Reasons for the Decision To facilitate the redevelopment of the Atherton Leisure Centre site, the Council intends to enter into a development agreement with the selected development partner who will undertake to deliver a new leisure centre together with some enabling development (residential properties) to provide a level of cross subsidy to the cost of the leisure centre. In order to achieve a practical completion date which ensures that the new leisure centre is open to the public in April 2015, it will be necessary to carry out enabling works in advance of achieving planning consent. The advance works will include demolition and asbestos surveys, asbestos removal, ground investigation works and soft strip out of the existing building. The advance works will allow the selected development partner to demolish the existing building directly after planning consent is gained, should this be granted. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

On 25th October 2012, the Mayor in consultation with Cabinet agreed to:

1. approve the selection of Mulalley & Company Limited in principle as the development partner- as per the recommendations following the tender exercise and for the capital sum outlined in the exempt Appendix A of the 25th October 2012 Cabinet report - to oversee the final design and programme of works, including demolition of the current building in order to re-provide the longer-term replacement facility on the site; and

2. approve the programme of works as proposed by the preferred development partner including the new build leisure centre, residential units and demolition programmes.

The Mayor also agreed, in line with the Scheme of Delegations, to;

3. approve the waiver of all relevant Contract Standing Orders and Contracts Procedure Rules that are required to be waived in order to follow the development agreement and procurement of the works contract as appropriate;

4. delegate authority to the Chief Executive in consultation with the Director of Strategic Regeneration Planning and Olympic Legacy, the Director of Business Systems, Property and Commercial Development the Director of Legal, People and Change and the Executive Members for Housing and Customer Services, Infrastructure and Environment, Regeneration and Strategic Planning to agree with the selected development partner a final works programme which includes design development, demolition works, building works and the associated procurements enabling the capital works to proceed at the Atherton Leisure Centre site; and

5. delegate authority to the Director of Business Systems, Property and Commercial Development to approve the final terms for the disposal of that portion of the site which is not to be used for the leisure centre for residential development in accordance with the bid put forward by the recommended development partner.

In order to meet the final completion date for the construction of the new leisure centre, as identified in the programme of works noted at item 2 above, it is necessary to commission enabling works comprising demolition and asbestos surveys, asbestos removal, ground investigation works and soft strip out of the existing building. The enabling works form part of the overall programme of works but are scheduled to be carried out prior to satisfaction of all conditions precedent in the development agreement, therefore it is necessary to facilitate this using an Advance Works Building Contract, separate to the main building contract.

The report seeks approval to let and fund, from the Capital allowance for the project, an Advance Works Building Contract. The Advance Works Building Contract value is estimated at £500K - £1 million (dependent upon the results of the asbestos survey). The selected development partner, Mulalley & Company Limited, have accounted for the cost of the advance works within their tender return. The cost will be drawn from the Capital allocation of £14.7m for the project, approved by the Mayor and Cabinet in February 2012.

The approval to proceed with an Advance Works contract is sought at this time in order to achieve the key programme date of April 2015 for the opening of the new leisure centre to the public.

Deferring the decision is likely to impact upon the business critical deadline of April 2015.

Recommendations

The Mayor is asked to :

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Atherton Leisure Centre: Advance Works Building ContractReport 104 KB DownloadRead as text
PDF
Report Part BReport 53 KB Download

At this meeting

Whole meeting

Who was there

12 of 15 attended
SR
Sir Robin WalesChair, present
AB
Councillor Andrew BaikieMember, non-voting, present
PB
Councillor Paul BrickellMember, non-voting, present
RC
Councillor Richard CrawfordMember, non-voting, present
CF
Councillor Clive FurnessMember, non-voting, present
LH
Councillor Lester HudsonMember, non-voting, present
AK
Councillor Alec KellawayMember, non-voting, present
AM
Councillor Anthony McAlmontMember, non-voting, present
CM
Councillor Conor McAuleyMember, non-voting, present
RA
Councillor Riaz Ahmed MirzaMember, non-voting, present
RQ
Councillor Rev. Quintin PeppiattMember, non-voting, present
NW
Councillor Neil WilsonMember, non-voting, present

All 15 on the meeting page

On this subject at Newham

Search all
  1. Atherton Leisure Centre - Advance Works Building ContractThis decision
  2. Atherton Leisure Centre RedevelopmentAgreed
  3. Atherton Leisure Centre - Appointment of OperatorAgreed
  4. Atherton Leisure Centre - Approval of Option for the Leisure Centre and Related Decision(s) Regarding Procurement(s)Agreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies