The Executive Director of Resources and Commercial Development Directorate, in consultation with the Head of Legal and Governance agreed to enter into an early works package with Morgan Sindall at Calverton, Portway and Upton Cross Primary Schools at a cost of £1,168,891.47 Reasons for the decision Morgan Sindall have priced for both the project preliminaries as part of the early works proposal. The works to be carried out as the early works package will be dealt with in an “Open Book” method. This will ensure transparency and will provide our Quantity Surveyors with total visibility of the formulation of the sum to assess the price for all construction works. It should also be noted that employing this method of working will ensure that value for money is being achieved, and the market has been fully tested. Each element of work provided by Morgan Sindall or their sub-contractors must be competitive. As part of this “Open Book” method of working, Morgan Sindall will provide this documentation to our Quality Surveyors as proof that this has been carried out and to enable any required benchmarking to ensure that value for money is being achieved. This decision is subject to the call-in process as the decision was based on part exempt information. The call-in period will expire at 5pm on 22 April 2013
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
OFFICER KEY DECISION Decisions Delegated to Officers which are Key Decisions
Has this proposal been entered in the Forward Plan? Yes.
Title of Report: Proposed Date of Calverton, Portway and Upton Cross Primary Schools. Decision To approve early works package of construction works. 15 April 2013. Decision Maker: Wards Affected:
Chris Pope Executive Director of Resources and Commercial Calverton Primary Development, in consultation with the Director Legal People School is located in and Change Custom House Ward, Portway is located in West Ham Ward, and the Upton Cross Credon Site is located in Green Street West Ward. However the need to provide additional school places affects all Wards Purpose of Report This report requests approval to the early works package which will form part of the construction budget at Calverton, Portway and Upton Cross Schools at a value amounting to £1,168,891.47.
Exempt Information. Appendix A, is not for publication as it contains exempt information by virtue of category 3 of the Access to Information Procedure Rules set out in the Constitution pursuant to Schedule 12 Local Government Act 1972. It is considered that the public interest in maintaining the exemption outweighs the public interest in disclosing it as if the Authority disclosed the information about bid for works it is likely to affect the Council’s ability to receive competitive bids in the future.
Proposed Decision: The Executive Director of Resources and Commercial Development Directorate, in consultation with the Director Legal People and Change to enter into an early works package with Morgan Sindall at Calverton, Portway and Upton Cross Primary Schools at a cost of £1,168,891.47.
Reason for Proposed Decision: The Executive Director of Resources and Commercial Development, in consultation with the Director Legal People and Change agreed as a Chief Officer decision on 19 October 2012 to enter into a pre-construction agreement with Morgan Sindall for a construction project to expand Calverton, Portway and Upton Cross (Credon Centre site) Primary Schools via the Improvement Efficiency South East (IESE) (Hampshire) Framework. This was in accordance with the decision at Mayoral Proceedings on 24 May 2012 to; 1. Grant approval for officers to commence a procurement exercise for a construction project to expand Calverton, Portway and Upton Cross (Credon Centre site) Primary Schools via the Improvement Efficiency South East (IESE) (Hampshire) Framework.
2. To authorise the Executive Director of Resources and Commercial Development in consultation with the Director Legal People and Change if required to enter into a pre-construction agreement to progress the procurement and also where appropriate to enter into an enabling works(s) contract(s) subject to such action being within the budget provision and presenting no reputation or legal risk.
This report requests approval to the early works package which will form part of the construction budget at Calverton, Portway and Upton Cross Schools at a value amounting to £1,168,891.47, in accordance with the decision taken on 24 May 2012.
The award of the full construction package would be subject to Mayoral Proceedings which is scheduled to be considered at the meeting to be held on 20 June 2013.
It is essential that early works packages are progressed to enable Morgan Sindall to put in place resources to ensure key activities are carried out at the schools over the summer holidays. This would help to minimise disruption to the school and to reduce risk of delay to the programme. The Council would enter into an agreement with Morgan Sindall to carry out enabling works prior to committing to the full JCT Contract for each scheme.
The evaluation of the early works package is set out in the Exempt Appendix A to this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Advocacy Service - Permission toRESOLVED for the reasons set out in the report, the Corporate Director for Adults and Health in consultation with the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.