East Ham Town Hall Roof Repair / Replacement - (Main Hall)

Agreed Committee 3 papers

Mayoral Proceedings agreed this item on Monday 25 January 2016. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Decision The Mayor agreed the acceptance of the tender submitted by Southern Counties Roofing Contractors Ltd in the sum of £741,470 for roof replacement and associated work at East Ham Town Hall (Main Hall). Reasons for the Recommendation In order that construction works can progress to address condition issues and to protect the long term future of this important listed civic building. This decision is subject to the call-in process as the decision was based on exempt information. The call-in period will expire on 10 th February 2016
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

This report requests approval to accept the tender submitted by Southern Counties Roofing Contractors Ltd in the sum of £741,470 for roof replacement and associated work at East Ham Town Hall (Main Hall).

Executive Summary of Outcomes

 The project will result in repair and improvement to the roof of the main hall at East Ham Town Hall which will prevent future water ingress and damage to the building.

Recommendation

The Mayor is asked to:

1. Approve the acceptance of the tender submitted by Southern Counties Roofing Contractors Ltd in the sum of £741,470 for roof replacement and associated work at East Ham Town Hall (Main Hall).

General Report Template: Ver: 006 Last revised: April 2015 Reasons for the Recommendation

In order that construction works can progress to address condition issues and to protect the long term future of this important listed civic building.

The scheme of Delegation and the Council’s Contract Standing Orders requires that Mayoral approval is given to the commencement of a tendering exercise for the award of a contract which is above £500,000.

NAME OF LEAD OFFICER: Zoe Power POSITION: Head of Projects and Programmes

Originator of report: Zoe Power/Peter Anthony Tel no: 020 3373 7263 / 020 3373 0476 E-mail address: [email removed] [email removed]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report:

N/A

Copies of Background documents can be obtained from:

N/A

List of enclosures:

Appendix 1 Site Plan Appendix 2: Exempt Information Appendix 3 Tender Report (Exempt)

General Report Template: Ver: 006 Last revised: April 2015 1. Introduction and Background

1.1Approval was secured at Mayoral Proceedings on Friday 3rd July 2015 to begin the procurement process for roof replacement/repair works at East Ham Town Hall. Following a competitive tender exercise using Constructionline, this report requests approval to award the contract to Southern Counties Roofing Contractors Ltd for roof replacement and associated work at East Ham Town Hall (Main Hall).

1.2Funding has been identified for repairs to the roof and ceiling at East Ham Town Hall. Utilising this funding, emergency works have already been undertaken to secure the main hall ceiling to prevent the fibrous plaster falling to the ground. Further details are provided at Appendix 2 (exempt).

2. Key Considerations

2.1The roof has suffered from disrepair and water ingress for a number of years and this is impacting on the sub-structure beneath the roof. The construction project will prevent further deterioration to the roof and structures beneath it.

2.2The proposed works include (see site plan Appendix 1):  Erection of scaffold and temporary roof to all areas of roof renewal;  Strip existing roof coverings and inspection and repair of timberwork as necessary;  Lay new slates to main hall and adjacent lower roofs;  Renew all defective lead work, downpipes and guttering;  Repair brickwork and masonry to high level parapet only;  Upgrade lightning protection to current regulations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Roof Works EHTH -Roof Plan FinalAppendix 1 127 KB Download
PDF
East Ham Town Hall Roof Repair / Replacement: (Main Hall)Report 101 KB DownloadRead as text
PDF
East Ham Town Hall Roof Repairs Tender Award Part BReport 72 KB Download

At this meeting

Whole meeting

Who was there

1 of 3 attended
JM
James MartinSecretary, expected
SR
Sir Robin WalesChair, present
GA
Gemma AllenOfficer, expected

On this subject at Newham

Search all
  1. East Ham Town Hall Roof Repair / Replacement - (Main Hall)This decision
  2. The Crystxl Lounge Ltd 339 Barking Road East Ham E6 1LARefused
  3. Food and Wine Costcutter 169 High Street North East Ham E6 1JBRefused
  4. Brampton Manor Academy, Roman Road, East Ham, London, E6 3SQDeferred
  5. Variation Premises Licence Application for Altmore Arms Arms 185 Altmore Ave, East Ham, E6 2BTNoted
  6. 434 Barking Road East Ham London E6 2SAAgreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies