Decision For the reasons set out in the report, Cabinet RESOLVED to AGREE: i) To invite tenders for Domestic and Sexual Violence Women’s Refuge for a potential contract term of 3 years with the option to extend for up to a maximum of a further two years (1+1) at the sole discretion of the Council (3+1+1); ii) To delegate authority to the Executive Director for Strategic Commissioning, following consultation with the Director of Finance, and the Director of Legal and Governance to do anything necessary to give effect to the above, including contract award; iii) That the procurement would be undertaken via a restricted tendering procedure complying with the Public Contracts Regulations 2015 and internal procurement rules. iv) To delegate authority to the Executive Director for Strategic Commissioning to agree any future extension of the contract for a period of up to two years, on a 1+1 year basis. Alternatives Considered 1. Due to the high levels of risk faced by women in the Refuge, it is necessary that the provision is delivered by specialist providers that have relevant experience of delivering such services. This will include demonstrating that they comply with relevant quality standards and employ appropriately qualified staff; 2. External providers will bring processes and systems to contracts as ‘added value’. These include outcome monitoring mechanisms which allow us to measure the impact of the service on women and any accompanying children. Commissioning from the open market will provide an opportunity for a refreshed service specification, innovation in delivery and improved value for money. 3. The service will provide quality assurance for the council as the service will meet appropriate guidance, service standards and quality marks. 4. The supportive element of Refuge services have been commissioned from external providers since 2012. This ensures delivery by organisations with an appropriate track record, associated expertise and existing stakeholder relationships.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
Report title Request to Procure accommodation based Women’s Refuge Date of Meeting 21st January 2019 Lead Officer Fiona Hackland, Head of Rupi Bhandal – Senior and contact Commissioning – Public Health, Commissioner – Public Health, details Adults. Adults DDI: 0203 373 3314, Int: 33314 DDI: 0203 373 7858, Int: 37858 [email protected][email protected] Director, Job Grainne Siggins - Executive Director for Strategic title Commissioning. Lead Member Cllr Susan Masters - Statutory Lead member, Health and Adult Social Care
Key Decision? Yes Reasons: A key decision due to the cost of the procurement exercise. Exempt information & Grounds Wards Affected All Wards Appendices Equality Impact Assessment (if any)
1 Executive Summary The current Women’s Refuge contract is due to end on the 31st August 2019. Cabinet are asked to agree reprocurement of this contract.
2 Recommendations 2.1 Cabinet agree to invite tenders for Domestic and Sexual Violence Women’s Refuge for a potential contract term of 3 years with the option to extend for up to a maximum of a further two years (1+1) at the sole discretion of the Council (3+1+1).
2.2To delegate authority to the Executive Director for Strategic Commissioning, following consultation with the Director of Finance, and the Director of Legal and Governance to do anything necessary to give effect to the above, including contract award.
2.3Agree that the procurement will be undertaken via a restricted tendering procedure complying with the Public Contracts Regulations 2015 and internal
1 procurement rules.
2.4Delegate authority to the Executive Director for Strategic Commissioning to agree any future extension of the contract for a period of up to two years, on a 1+1 year basis.
3 Background 3.1 The London Borough of Newham (LBN) currently commissions 25 units of Refuge provision for women and children fleeing Domestic and Sexual Violence (DSV). The contract end date for provision is the 31st August 2019.
3.2The contract was initially granted as part of the London Borough of Tower Hamlets and London Borough of Newham Framework Agreement for Supporting People Services, and was awarded at Mayoral Proceedings in July 2012.
3.3The service area is funded general fund base budgets for Adult Social Care.
4 Key Considerations & Proposals 4.1 The proposed service offer will be for 25 units of Refuge provision, providing a safe haven for women and any accompanying children who are fleeing domestic and/or sexual violence.
4.2The contract between LBN and the provider will be for the care and support element of the service. As part of the bidding process, potential providers will be expected to source appropriate premises from an appropriate landlord that is suitable for a secure women’s Refuge. The contractual relationship for the premises, in which the service is based, will be between the provider and the landlord.
4.3The service will aim to provide: A survivor focussed model of support. Prompt and targeted support within a safe women-only environment that reduces risk and increases resilience. The addressing of the immediate and longer term physical, sexual and mental health needs of service users. Move-on of individuals onto appropriate accommodation as soon as it is safe to do so. Development of an individual’s independent living skills, to enable them to positively maintain a tenancy and live independently. Signposting to specialist services when necessary, and develop wider support networks that will enable each individual to reduce their reliance on the service. Support and advocacy for women to report violence to the Police and have access to appropriate legal and financial advice. Assessment of the practical and emotional support needs of residents to ensure appropriate evidence based interventions in the form of one to one support, group work and peer to peer support. Support should be a mixture of onsite support and referral and advocacy to specialist providers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.