Resolved

RESOLVED to AGREE i) The forward commitment to purchase of an in-borough, 152 Bedroom hotel which will be let on practical completion to Premier Inn Hotels Limited with a guarantee from Whitbread Group PLC as per the terms set out in Appendix 1/2; ii) The recommended funding / financing option from the Institutional Investor (Option 3 – see 4.6) to provide 100% of the capital required of £21.250m and additional transaction costs (stamp duty and professional fees) of £1.425m (£22.675m total) relating to the acquisition of Canning Town Premier Inn Hotel; and iii) The business case for acquisition following the positive outcome of substantial due diligence covering strategic, financial, property, asset and legal) which highlights the attractiveness of the investment. Alternatives considered 1) The only alternative considered is that the Council does nothing due to a lack of alternative in-borough’ investment: Council does nothing - The Council would withdraw its offer on the property, losing the certainty of revenue that would be generated from this transaction. The Council is under no obligation to purchase the property and could look for other investment opportunities. However, it is considered that this purchase represents a good opportunity to generate income and to contribute to reducing the budget gap. The in-borough pipeline of investment opportunities is very limited, and the property is available now and ready for exchange and completion following 3 months of thorough due diligence. If the Council did nothing, it would not be liable for the rent guarantee. Properties take time to acquire and choosing not to purchase the property would impact the ability to generate income. Withdrawal from this purchase would affect the overall pipeline and delay achievement of the strategy. As a reference, only two opportunities of interest have come to market in the last 9 months ‘in borough’. Given the limited in-borough pipeline of investment opportunities this could be the only viable opportunity for acquisition this year.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Rental EvidenceAppendix 3 41 KB Copy on its way
PDF
Recent Market TransactionsAppendix 4 80 KB Copy on its way
PDF
Brunel Street Works, Canning Town HotelReport 157 KB Copy on its way

At this meeting

Whole meeting

On this subject at Newham

Search all
  1. Brunel Street Works, Canning Town HotelThis decision
  2. Land At 10 To 11 Brunel Street And 36 To 48 Shirley Street, Canning Town, London E16 1HUAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies