Enabling new Market Rent and London Affordable Rented Housing Development at the Brickyard Scheme , Barking Rd/St. John's Rd, East Ham (Populo Living - Red Door Ventures)

Agreed Executive 3 papers

Cabinet agreed this item on Wednesday 13 May 2020. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision For the reasons set out in the report, Cabinet RESOLVED to AGREE: i) To approve £35.3m of funding to RDV for the Brickyard scheme on the former car park located at Barking Road/St. John’s Road E6 1NN. This comprises Newham equity and loan funding to RDV of up to £35.3m for the Development Phase; ii) To delegate to the Corporate Director of Resources in consultation with the Cabinet Member Finance and Corporate Resources, approval of variances to these funding figures of up to 5%. Any variations above 5% overall will be brought back to Cabinet; and iii) To approve LBN entering into an Entrustment Deed with RDV as necessary for compliance with State Aid law as outlined in Section 8.2 below Alternatives considered The alternatives considered are as follows:- · Council develops the sites directly; · Council develops the affordable sites directly; · Council sells the sites to a third party; · Council transfers the land to RDV but does not fund the development; · Council does nothing. Council develops the sites directly - As the land is owned by London Borough of Newham, the Council could implement the planning permissions secured by RDV, with minor amendments. This approach however would entail significant delay and expense for the Council in establishing an in-house development team with expertise in both market rented and affordable homes and capable of delivering complicated mixed-use schemes such as Brickyard. It would be thus be impractical to pursue this option and for this reason, this approach has been discounted. Council develops the affordable sites directly –The Council’s Housing Delivery Team is development managing the balance of the AHfN programme (i.e. all schemes that are not RDV affordable homes) and the Council’s HRA is already funding those developments. The Council must achieve a balance between investing in new affordable homes through its HRA, and using other resources to improve and update existing council homes. Council sells the sites to a third party - Delivery through an external third party developer or Registered Provider would result in the Council (other than in its capacity as Local Planning Authority) having no control over the sites. The council would not benefit directly from any of the financial upside in respect of development profit, margin on lending, dividends. The Council would not benefit from any capital appreciation in the value of the completed investment assets. Many local authorities have set up Local Housing Companies to control delivery quality and gain the financial upside of the profit margin and the lending rate. For this reason, this option has been discounted. Council transfers the land to RDV but does not fund the development - This investment made by Newham has been shown to finance the cost of the loan and provide a lending margin and dividend back to the Council in excess of target hurdle rates. If a third party funded the development, while they would take on risk, any financial benefit would go to the funder rather than the Council. For this reason it is considered ...
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1Red Door Ventures (RDV) is the Council’s wholly-owned housing development company, and is an integral part of the Council’s programme for building over 1,000 new homes at social rent levels. This Report seeks approval for the necessary funding to enable RDV to deliver a mixed-use scheme at the former

1 Council car park site located at Barking Rd/St. John’s Rd. E6. The scheme includes a residential element of 70 market rented and 28 London Affordable Rented homes, together with two commercial units at ground floor and a commercially operated gym at first floor. This development (known as the ‘Brickyard scheme’) has planning consent, and is included within the RDV Business Plan approved at Cabinet on 18th February. The site disposal to RDV was approved by Cabinet on 3rd December 2019.

Recommendations

For the reasons set out in the report and its appendices, Cabinet is recommended to:

2.1Approve £35.3m of funding to RDV for the Brickyard scheme on the former car park located at Barking Road/St. John’s Road E6 1NN. This comprises Newham equity and loan funding to RDV of up to £35.3m for the Development Phase.

2.2Delegate to the Corporate Director of Resources in consultation with the Cabinet Member Finance and Corporate Resources, approval of variances to these funding figures of up to 5%. Any variations above 5% overall will be brought back to Cabinet.

2.3To approve LBN entering into an Entrustment Deed with RDV as necessary for compliance with State Aid law as outlined in Section 8.2 below

3 Background 3.1 Housing is one of the Council’s key priorities with over 27,000 people on the Housing Register (as at March 2020) and 5,420 households in temporary accommodation. The Mayor pledged to start building at least 1,000 new council owned homes at social rent levels by 2022 and to start building 100 of these by May 2019. These 100 starts were achieved as part of RDV’s initial Didsbury package of developments.

3.2The Council was successful in its bid for grant funding from the GLA as part of the Building Homes for Londoners programme, being awarded £107m in total.

3.3The Council has previously approved two funding packages for RDV totalling circa £180M for the delivery of 296 market rent homes, 230 affordable homes, a 1,050sqm community hub and 2,310sqm of commercial space. This is the third package of funding to be requested by RDV following its re-purposing to deliver more affordable homes under Mayor Fiaz. 3.4 A cabinet report on 3rd December 2019 approved disposal of the Brickyard site to RDV for a leasehold term of 250 years.

3.5A cabinet report on 18th February 2020 approved RDV’s Business Plan for 2020- 21. This Business Plan included the Brickyard site within RDV’s development

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St Johns Road Car Park Site Location PlanAppendix 1 451 KB Download
PDF
RDV EQIA (Oct Cabinet)Appendix 3 241 KB Download
PDF
Enabling new Market Rent and London Affordable Rented Housing Development at the Brickyard Scheme , Barking Rd/St. John's Rd, East Ham (Populo Living: Red Door Ventures)Report 527 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
JF
Jayne FisherCouncil Staff, expected
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
JG
Councillor John GrayMember, present
CM
Councillor Charlene McLeanMember, apologies
ZA
Councillor Zulfiqar AliMember, present
JM
Councillor Julianne MarriottMember, present
JB
Councillor James BecklesMember, present
TP
Councillor Terence PaulMember, present
SJ
Councillor Sarah Jane RuizMember, apologies due to council business
JA
Councillor James AsserMember, present
DF
Daniel FenwickOfficer, expected
AL
Althea LoderickOfficer, expected

On this subject at Newham

Search all
  1. Enabling new Market Rent and London Affordable Rented Housing Development at the Brickyard Scheme , Barking Rd/St. John's Rd, East Ham (Populo Living - Red Door Ventures)This decision
  2. Enabling new Market rent; London Affordable Rented and Shared Ownership housing development at Plaistow (Red Door Ventures)Agreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies