Expansion of Lister School: Procurement of Construction Contracts and Allocation of Additional Basic Need Capital Funding

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 13 April 2021. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

For the reasons set out in the report and its appendix, Cabinet RESOLVED to AGREE: i) To allocate additional Basic Need Capital Grant Funding of £3,110,360 to the project, as set out at paragraph 8.1.2 of the report, subject to planning and other statutory consents; ii) Award a contract in the sum of £3,673,372 to Neilcott Construction Ltd. for internal remodelling works and external landscaping works to expand Lister School, as set out at paragraph 3.7.3 and section 4 of the report; iii) To authorise the Corporate Director Children and Young People, following consultation with the Cabinet Member for Education, to agree the detailed terms of the above contracts, and that a report be submitted to the July 2021 Cabinet meeting setting out details of the Council’s overall approach to community consultation with regards to the project and other projects across the school build programmes; and iv) To authorise the Corporate Director of Resources, following consultation with the Cabinet Member for Education, to enter into Deeds of Variation to the PFI Project Agreement to reflect the changes in respect of construction works packages, as set out at paragraph 4.11 of the report. Alternatives Considered Not to provide additional places - the Council had a statutory duty to provide sufficient places. There continued to be significant additional pressure on secondary school places; since September 2019 an additional 11 forms of entry had been provided to meet demand. To meet demand for September 2021 onwards, four further forms of permanent entry were planned at Little Ilford (two forms) and Lister Schools (two forms). Data from school applications for pupils applying for Year 7 places for 2021 confirmed that the additional provision was needed in order to ensure every child could be offered a place. To provide additional places at another school - in 2018/19 all Newham secondary schools were invited to express interest in expanding to meet forecast demand for 2021. Three schools expressed interest. A number of secondary schools had already been expanded and there was little scope to expand them further, which limited the response from other schools. Two of the three schools were selected (Little Ilford and Lister) on the basis that they were popular and good performing schools with the capacity to expand. The proposal was now well advanced and pursuing an alternative site would result in considerable delay. To provide places at a new school - land availability to build a new school was limited and would need to be identified. It had not been possible to identify a site for a new secondary school, particularly in the east of the borough where secondary school places were in shorter supply. The difficulty in identifying suitable site(s) was evidenced by the prolonged search by the LocatED to identify a site for 2 x new all-through Free School Academies in the borough. All new schools must be Free School Academies. A Free School Academy sponsor would need to be identified. Different space configuration to achieve expansion - different options ...
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

LONDON BOROUGH OF NEWHAM

CABINET

Report title Expansion of Lister School: Procurement of Construction Contracts and Allocation of Additional Basic Need Capital Funding Date of Meeting 13th April 2021 Lead Officer and Zoe Power, Head of Projects and Programmes contact details External Telephone Number: 0203 3737263 Email address : [email removed]

Corporate Tim Aldridge, Corporate Director of Children and Young Director People Lead Member Cllr Sarah Ruiz, Cabinet Member Children's Social Care and Education Key Decision? Yes Reason: Involves expenditure or savings of £500,000 or more. Decision reserved for Cabinet with expenditure over £1m and affects two or more wards Exempt No information & Grounds Wards Affected Lister School is in Plaistow North Ward. Students, including students with Special Educational Needs and Disabilities (SEND), who attend the school live across the Borough and the need to provide additional Secondary School places affects the whole Borough and therefore all wards are affected. Students attending the JFK school annexe will come from all areas of the Borough and therefore all wards are affected. Appendices 1.Updated Equality Impact Assessment (if any)

1 Executive Summary 1.1 Following consideration of a School Place Planning Update by Cabinet on 21st January 2019, which allocated Basic Need grant funding towards secondary school expansion projects to meet forecast demand for places, Cabinet on 3rd December 2019 agreed that the Council should invite tenders for an expansion project at Lister School. This report updates Cabinet on the tender process and recommends award of a contract for part of the expansion works.

1 1.2 Commencement of the expansion project has been delayed pending resolution of a longstanding dispute between the Council and Lister School related to school contributions payable towards the cost of PFI services. This has now been resolved. Following agreement of Cabinet on 3rd November 2020, Heads of Terms have been agreed and signed by both parties and a binding Settlement Agreement is in preparation.

1.3The scope and phasing of the project has changed, with resultant increases in project costs compared to December 2019 estimates. This report requests authorisation for additional Basic Need capital funding to be allocated towards this project.

1.4Following consideration of a report on Special Educational Needs and Disability (SEND) Provision on 6th October 2020 Cabinet agreed to allocate education capital funding to provide a special school satellite annex of the JFK Special School on the Lister School premises and to appoint Module AR Limited (M- AR) to undertake construction works to provide this accommodation. These works will progress concurrent with the expansion project.

1.5As Lister is a PFI school this report also seeks approval to enter into Deeds of Variation to the PFI Project Agreement, (the contract between the Council and the PFI Company), in respect of the proposed construction works on site. PFI services at this school include a range of hard facilities management services (planned and reactive repairs and maintenance and lifecycling), plus caretaking and security services but exclude catering, cleaning, waste management and pest control. Revenue payments, called the Unitary Charge, are made monthly to the PFI contractor by the Council over the 25 year term of the PFI Contract to cover repayment of the cost of the initial design and building of the new school and its ongoing management. The report sets out the revenue implications arising from expansion of Lister School and provision of the JFK annexe.

2 Recommendations 2.1 For the reasons set out in the report and its appendices Cabinet is requested to:

2.1.1 Agree to allocate additional Basic Need capital grant funding of £3,110,360 to the project, as set out at paragraph 8.1.2 of this report, subject to planning and other statutory consents;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Updated Equality Impact AssessmentAppendix 1 97 KB Download
PDF
Expansion of Lister School: Procurement of Construction Contracts and Allocation of Additional Basic Need Capital FundingReport 162 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
JC
Jane CustanceCouncil Staff, expected
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
CM
Councillor Charlene McLeanMember, apologies
ZA
Councillor Zulfiqar AliMember, present
JB
Councillor James BecklesMember, present
TP
Councillor Terence PaulMember, present
SJ
Councillor Sarah Jane RuizMember, present
JA
Councillor James AsserMember, present
SM
Councillor Shaban MohammedMember, present
CL
Councillor Carleene Lee-PhakoeMember, present
AL
Althea LoderickOfficer, expected
DF
Daniel FenwickOfficer, expected

All 14 on the meeting page

On this subject at Newham

Search all
  1. Expansion of Lister School: Procurement of Construction Contracts and Allocation of Additional Basic Need Capital FundingThis decision
  2. Expansion of Lister School: Pre Procurement ReportAgreed
  3. Proposed Expansion of Lister Secondary School: Issue of Public NoticeApproved

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies