New Homes for Newham Programme - 2021-22 Contract Awards (Post December 2021 Cabinet Approval)

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 8 March 2022. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

For the reasons set out in the report and its appendices, Cabinet RESOLVED to AGREE : i) To entering into a JCT Design & Build contract with Kind & Company for the sum of £7,268,347 for the Morse Close scheme for 17 homes at London Affordable Rent.; ii) To entering into a JCT Design & Build contract with Bugler Developments Limited for the sum of £19,772,838.59 for the Burgoyne Depot scheme for 32 homes at London Affordable Rent and 16 homes for shared ownership; iii) To enter into a JCT Design & Build Contract with Higgins Partnerships PLC for the sum of £23,418,330 for the John Street scheme for 70 homes at London Affordable Rent; iv) The commencement of a below threshold works procurement exercise using either a compliant framework or a restricted tender exercise using a restricted process in relation to the refurbishment of Arragon Road (relocating the Boxing Club at John Street),at the estimated value of £3m; v) To delegate authority to Corporate Director of Inclusive Economy & Housing in consultation with the Lead Member for Inclusive Economy and Housing Delivery, Air Quality Climate Emergency, and Lead Member for Housing Services to accept the final tender price, award and enter into a JCT Design & Build contract for the sum of up to · £30,970,000 for the Hathaway Crescent scheme for 72 homes at London Affordable Rent. · £15,000,000 for the Army & Navy and New Barn Street scheme for 32 homes at London Affordable Rent. vi) An update on the above contracts will be provided in a future Cabinet paper on the AHfN programme. Alternatives Considered 1) Alternative frameworks may have been used however the whole market is experiencing the same supply constraints and price inflation pressures and a similar outcome would have been likely. 2) To do nothing - not delivering these schemes means that the council fails to deliver the Affordable Housing for Newham Programme. The GLA will not extend the duration of the programme beyond 2022-23 starts.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1On the 7th December 2021 Newham’s Cabinet delegated the approval of eight individual scheme build contracts up to a combined value of £149m for 348 homes. These schemes form part of the Affordable Homes for Newham programme delivering the Corporate objective to secure 1,000 new Council owned homes at social rent levels to be started by May 2022.

1.2The December paper stated that timescales were very tight to deliver contractual starts to meet the GLA target for start on sites dates and the construction market was subject to tender price inflation.

1.3Good progress has been made on delivering the programme but three tendered schemes have values higher than the caps Cabinet approved in December 2021.

1.4The refurbishment of the Arragon Road building to accommodate the relocation of the boxing club from John Street is required to be tendered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Homes for Newham Programme: 2021-22 Contract Awards (Post December 2021 Cabinet Approval)Report 503 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
AH
Asmat HussainCouncil Staff, expected
JC
Jane CustanceCouncil Staff, expected
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
CM
Councillor Charlene McLeanMember, apologies
ZA
Councillor Zulfiqar AliMember, present
JB
Councillor James BecklesMember, apologies
TP
Councillor Terence PaulMember, present
SJ
Councillor Sarah Jane RuizMember, present
JA
Councillor James AsserMember, present
SM
Councillor Shaban MohammedMember, present
CL
Councillor Carleene Lee-PhakoeMember, present
AL
Althea LoderickOfficer, expected

All 15 on the meeting page

On this subject at Newham

Search all
  1. New Homes for Newham Programme - 2021-22 Contract Awards (Post December 2021 Cabinet Approval)This decision
  2. Delivering new homes at Pier Rd & CyprusAgreed
  3. Affordable Homes for Newham, contract variationsAgreed
  4. New Homes for Newham Programme - 2022-23 Leyes Road Contract AwardAgreed
  5. 2021-2026 GLA Funding Contract and Future Affordable Homes for Newham ProgrammeAgreed
  6. New Homes for Newham Programme Delivery of Shared OwnershipAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies