Cabinet, Tuesday 20 December 2022

Shipman Youth Zone - Contract Award

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 20 December 2022. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

For the reasons set out in the report and its appendices, Cabinet RESOLVED to AGREE: i) The proposal to increase the project budget from £6.5 million to £9.2 million including £0.2m of GLA grant funding referred to in (ii) below; ii) The acceptance of LLDC grant funding, in the sum of £212,000 from the LLDC’s Carbon Offset Fund, for the installation of mechanical and electrical systems to make the new youth zone building net carbon neutral in use, subject to legal review of the agreement; and iii) Subject to agreeing increased budget in (i) above, approval to enter the stage two contract award (JCT (Joint Contracts Tribunal) Design & Build (2011) with Newham amendments) with Neilcott Construction Ltd (Company No. 02015011) in the sum of £8,295,023 for a 46-week contract period. Alternatives considered 1) Do nothing – This is disregarded as a failure to provide a safe space for young people will have a detrimental impact on the Council’s ability to deliver the corporate priorities of providing a high quality, co-produced youth offer that provides a varied and inclusive range of activities.” The Mayor’s vision is that children and young people in Newham should have access to the best youth service in London - providing young people with spaces to enjoy, support to achieve their best, and opportunities to make a difference in their community. 2) Stage 2 of the project could be re-tendered as a new single-stage contract. This is not being proposed as it would add significant delay to the programme without any indication pricing would be lower. There would also be a claim of c.£100k from Neilcott for work already undertaken, on the understanding they would deliver stage 2 of the tender. 3) Options to reduce the scope of the project have also been considered, to establish the impact on service delivery of reducing costs to within the approved budget. 4) The options considered were to: • Omit the sports hall superstructure but undertake foundation works to preserve future flexibility • Omit the sports Hall completely • Omit the sports Hall completely and make additional changes to main building 5) All the cost reduction options considered as part of value engineering would have a significant and adverse impact on the Youth Zone and the delivery of benefits to Newham’s young people. The sports hall is considered essential and therefore omitting the sports hall will be detrimental to the stated ambition and intention for the project. 6) Additional changes to the main building would reduce function room space in the building, so impacting the intended programmes that could be delivered from the Youth Zone and the stated aspirations for this site. For the reasons set out in the report and its appendices, Cabinet RESOLVED to AGREE: i) The proposal to increase the project budget from £6.5 million to £9.2 million including £0.2m of GLA grant funding referred to in (ii) below; ii) The acceptance of LLDC grant funding, in the sum of £212,000 from the LLDC’s Carbon Offset Fund, for the installation of mechanical and electrical systems to make the new youth zone building net carbon neutral in use, subject to legal review of the agreement; and iii) Subject to agreeing increased budget in (i) above, approval to enter the stage two contract award (JCT (Joint Contracts Tribunal) Design & Build (2011) with Newham amendments) with Neilcott Construction Ltd (Company No. 02015011) in the sum of £8,295,023 for a 46-week contract period. Alternatives considered 1) Do nothing – This is disregarded as a failure to provide a safe space for young people will have a detrimental impact on the Council’s ability to deliver the corporate priorities of providing a high quality, co-produced youth offer that provides a varied and inclusive range of activities.” The Mayor’s vision is that children and young people in Newham should have access to the best youth service in London - providing young people with spaces to enjoy, support to achieve their best, and opportunities to make a difference in their community. 2) Stage 2 of the project could be re-tendered as a new single-stage contract. This is not being proposed as it would add significant delay to the programme without any indication pricing would be lower. There would also be a claim of c.£100k from Neilcott for work already undertaken, on the understanding they would deliver stage 2 of the tender. 3) Options to reduce the scope of the project have also been considered, to establish the impact on service delivery of reducing costs to within the approved budget. 4) The options considered were to: • Omit the sports hall superstructure but undertake foundation works to preserve future flexibility • Omit the sports Hall completely • Omit the sports Hall completely and make additional changes to main building 5) All the ... view the full minutes text for item 8.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
_Shipman MRP calcsAppendix 2 422 KB Copy on its way
PDF
Shipman Youth Zone: Contract AwardReport 290 KB Copy on its way

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies