Highways Framework Contracts Inflation Adjustment 2023

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 16 February 2023. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

For the reasons set out in the report Cabinet RESOLVED to AGREE: i) To note the spiralling increase of inflation and the pressure that this puts on the current service providers due to the unsustainability of certain rates prescribed in the contract; ii) To approve the amendment of the NEC Highways Framework Contracts between the Council and the Contractors listed at paragraph 3.2 of this report (the “Contracts”) to invoke Clause X1 one year ahead of schedule; iii) To approve the amendment of the Contracts to include a review of Clause X1 on a quarterly basis until the second anniversary of the Contract, 1 February 2024; and iv) To delegate to the Corporate Director of Environment & Sustainable Transport in consultation with Lead Member for Environment and Sustainable Transport to continue to undertake a quarterly review of Clause X1 within the contract period until a point in time where inflation has stabilised. Alternatives considered 1. One option was to continue as is and do nothing, with a certainty that at some point in the very near future, contractors will stop work for the Council, until the X1 Clause is invoked in February 2024. If this was to happen, there is potential for loss of confidence in the Council by our external funding partners, for some of the key capital projects that are due to be implemented next financial year, such as The Royal Docks Corridor and Levelling Up Fund. There would also be a reputational issue for the Council as it would not be able to deliver on its corporate priorities. Service delivery would also be at risk. 2. Another alternative was to delay projects if the contractors refuse to deliver until February 2024. However, this has its own risk, if inflation continues to rise, the rates will continue to rise again in 2024 and the cost to deliver would have included a further year of inflation rises. Hence it would actually cost more to deliver the same in future years then it would if delivered next financial year. 3. An alternative was to make use of the TfL HMPF for all projects that other contractors refuse to take on. However as this will have a price adjustment applied in April, the rates would be similar to the rates within the Highways Scheme and Planned Maintenance Frameworks Contracts (Lot 1 and Lot 2). 4. A further alternative was to undertake a procurement exercise now, covering any potential gap between contractors refusing to undertake work and when the actual Clause X1 is invoked in February 2024. This would be a timely process and would most likely not be in place until next autumn, potentially putting the Council in a position where it may not have a contractor to undertake highway works. It is also expected that any such exercise would be at current market rates in an unstable market, plus contractors would also include high risk allowances, built into their submitted rates, to safeguard themselves against further unknown inflation increases. 5. For ... For the reasons set out in the report Cabinet RESOLVED to AGREE: i) To note the spiralling increase of inflation and the pressure that this puts on the current service providers due to the unsustainability of certain rates prescribed in the contract; ii) To approve the amendment of the NEC Highways Framework Contracts between the Council and the Contractors listed at paragraph 3.2 of this report (the “Contracts”) to invoke Clause X1 one year ahead of schedule; iii) To approve the amendment of the Contracts to include a review of Clause X1 on a quarterly basis until the second anniversary of the Contract, 1 February 2024; and iv) To delegate to the Corporate Director of Environment & Sustainable Transport in consultation with Lead Member for Environment and Sustainable Transport to continue to undertake a quarterly review of Clause X1 within the contract period until a point in time where inflation has stabilised. Alternatives considered 1. One option was to continue as is and do nothing, with a certainty that at some point in the very near future, contractors will stop work for the Council, until the X1 Clause is invoked in February 2024. If this was to happen, there is potential for loss of confidence in the Council by our external funding partners, for some of the key capital projects that are due to be implemented next financial year, such as The Royal Docks Corridor and Levelling Up Fund. There would also be a reputational issue for the Council as it would not be able to deliver on its corporate priorities. Service delivery would also be at risk. 2. Another alternative was to delay projects if the contractors refuse to deliver until February 2024. However, this has its own risk, if inflation continues to rise, the rates will continue to rise again in 2024 and the cost to deliver would have included a further year of inflation rises. Hence it would actually cost more to deliver the same in future years then it would if delivered next financial year. 3. An alternative was to make use of the TfL HMPF for all projects that other contractors refuse to take on. However as this will have a price adjustment applied in April, the rates would be similar to the rates within the Highways Scheme and Planned Maintenance Frameworks Contracts (Lot 1 and Lot 2). 4. A further alternative was to undertake a procurement exercise now, covering any ... view the full minutes text for item 13.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report seeks Cabinet approval to amend a condition in the Highways Scheme and Planned Maintenance Frameworks Contracts (Lot 1 and Lot 2) 2021 to 2025. Clause X1, Inflation Adjustment, is not due to be invoked until the second anniversary of the contract, February 2024. However considering the current rate of inflation and the relative speed of change, it is proposed to invoke this clause one year earlier, and to amend the review periods of the clause within the contract.

1.2The contract award of the Highways Scheme and Planned Maintenance Frameworks Contracts (Lot 1 and Lot 2) was presented to Cabinet on 7 December 2021 (see Background Information).

1.3This is being proposed to compensate the exceptional circumstances with rates of inflation rising, well above estimates that could not have been reasonably anticipated at the time that the contracts were negotiated. This also helps ensure that the Council has framework contractors who can undertake planned schemes and planned maintenance during 2023 and 2024.

2 Recommendations 2.1 For the reasons set out in the report and its appendices, Cabinet, is recommended to: 2.1.1 Note the spiralling increase of inflation and the pressure that this puts on the current service providers due to the unsustainability of certain rates prescribed in the contract. 2.1.2 Approve the amendment of the NEC Highways Framework Contracts between the Council and the Contractors listed at paragraph 3.2 of this report (the “Contracts”) to invoke Clause X1 one year ahead of schedule. 2.1.3 Approve the amendment of the Contracts to include a review of Clause X1 on a quarterly basis until the second anniversary of the Contract, 1 February 2024. 2.1.4 Delegate to the Corporate Director of Environment & Sustainable Transport in consultation with Lead Member for Environment and Sustainable Transport to continue to undertake a quarterly review of Clause X1 within the contract period until a point in time where inflation has stabilised.

2 3 Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Framework Contracts Inflation Adjustment 2023Report 294 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
JA
Councillor James AsserMember, present
CM
Councillor Charlene McLeanMember, present
ZA
Councillor Zulfiqar AliMember, present
NW
Councillor Neil WilsonMember, present
SJ
Councillor Sarah Jane RuizMember, apologies
CL
Councillor Carleene Lee-PhakoeMember, present
SM
Councillor Shaban MohammedMember, present
JG
Councillor Joshua GarfieldMember, present

On this subject at Newham

Search all
  1. Highways Framework Contracts Inflation Adjustment 2023This decision
  2. Award of Highways Frameworks Contracts 2026Agreed
  3. Highways Infrastructure Asset Management Framework 2023Agreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies